Dacy Building Services Ltd v IDM Properties LLP
The Defendant, IDM Properties LLP, has a realistic prospect of succeeding in its defence that there was no contract between it and Dacy, and thus the adjudicator lacked jurisdiction. The dispute turns on conflicting evidence and cannot be resolved summarily.
- Parties
- Claimant: Dacy Building Services Limited; Defendant: IDM Properties LLP
- Jurisdiction
- England and Wales
- Judgment Date
- 25 November 2016
- Procedural Posture
- Application for Summary Judgment / Ruling on Summary Judgment Enforcement of Adjudicator's Decision
- Outcome
- Application for summary judgment dismissed
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Oral Contracts, Summary Judgment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Dacy Building Services Limited
Claimant
IDM Properties LLP
Defendant
Procedural Posture
Application for Summary Judgment / Ruling on Summary Judgment Enforcement of Adjudicator's Decision
Legal Issues
- 1 Whether there was a contract between Dacy and IDM Properties LLP
- 2 Whether the adjudicator had jurisdiction to determine his own jurisdiction
- 3 Whether IDM Properties LLP submitted to the adjudicator's jurisdiction
Ratio Decidendi
The Defendant, IDM Properties LLP, has a realistic prospect of succeeding in its defence that there was no contract between it and Dacy, and thus the adjudicator lacked jurisdiction. The dispute turns on conflicting evidence and cannot be resolved summarily.
Court Disposition
Application for summary judgment dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment