Dacy Building Services Ltd v IDM Properties LLP
The court found, on the evidence, that an oral contract was concluded between Dacy Building Services Limited and IDM Properties LLP at the meeting on 3 December 2015. The contract was for Dacy to perform works at the project and be paid by IDM Properties. This finding established that the adjudicator had jurisdiction to make the decision in favour of Dacy. The decision is based on the credibility of the witnesses, the contemporaneous documents, and the commercial context, which made it highly unlikely that Dacy would have contracted with HOC. The court rejected IDM Properties' version of events and found that the oral agreement was intended to create legal relations and was binding.
- Parties
- Claimant: Dacy Building Services Limited; Defendant: IDM Properties LLP
- Jurisdiction
- England and Wales
- Judgment Date
- 05 February 2018
- Procedural Posture
- Construction Contract Dispute (adjudication Enforcement) / Trial of Preliminary Issue After Summary Judgment Application
- Outcome
- Judgment for the Claimant (Dacy Building Services Limited)
- Legal Topics
- Adjudication Enforcement, Oral Contracts, Jurisdiction of Adjudicator, Contract Formation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Dacy Building Services Limited
Claimant
IDM Properties LLP
Defendant
Procedural Posture
Construction Contract Dispute (adjudication Enforcement) / Trial of Preliminary Issue After Summary Judgment Application
Legal Issues
- 1 Whether an oral contract was formed between Dacy Building Services Limited and IDM Properties LLP on 3 December 2015
- 2 Whether the adjudicator had jurisdiction to make the decision in favour of Dacy
Ratio Decidendi
The court found, on the evidence, that an oral contract was concluded between Dacy Building Services Limited and IDM Properties LLP at the meeting on 3 December 2015. The contract was for Dacy to perform works at the project and be paid by IDM Properties. This finding established that the adjudicator had jurisdiction to make the decision in favour of Dacy. The decision is based on the credibility of the witnesses, the contemporaneous documents, and the commercial context, which made it highly unlikely that Dacy would have contracted with HOC. The court rejected IDM Properties' version of events and found that the oral agreement was intended to create legal relations and was binding.
Court Disposition
Judgment for the Claimant (Dacy Building Services Limited)
Orders
- The decision of the adjudicator is enforced.
- Judgment is entered for Dacy Building Services Limited in the sum found by the adjudicator.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment