South Coast Construction Ltd v Iverson Road Ltd
The court held that the adjudicator had jurisdiction to decide all questions of delay, extensions of time, liquidated damages, and prolongation costs because these issues were necessarily encompassed within the dispute referred and further brought into scope by the defendant's own cross-claims. The defendant's...
Source-derived case information.
- Parties
- Claimant: South Coast Construction Limited; Defendant: Iverson Road Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 19 January 2017
- Procedural Posture
- Civil (construction Contract Dispute) / Judgment on Summary Judgment Application to Enforce Adjudicator's Decision
- Outcome
- Judgment for the claimant; summary judgment granted enforcing the adjudicator's decision.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Moratorium Under Insolvency Act, Summary Judgment, Liquidated Damages, Extension of Time
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
South Coast Construction Limited
Claimant
Iverson Road Limited
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Judgment on Summary Judgment Application to Enforce Adjudicator's Decision
Legal Issues
- 1 Whether the court should grant permission to continue proceedings during a moratorium under the Insolvency Act 1986
- 2 Whether the adjudicator had jurisdiction to decide issues of extension of time and prolongation costs
- 3 Whether the adjudicator's decision should be enforced by summary judgment
Ratio Decidendi
The court held that the adjudicator had jurisdiction to decide all questions of delay, extensions of time, liquidated damages, and prolongation costs because these issues were necessarily encompassed within the dispute referred and further brought into scope by the defendant's own cross-claims. The defendant's conduct in issuing serial NOIs and failing to notify the claimant and the court was improper. The moratorium did not bar enforcement, and the adjudicator's decision was binding and enforceable. Judgment was entered for the claimant for the sums awarded by the adjudicator.
Court Disposition
Judgment for the claimant; summary judgment granted enforcing the adjudicator's decision.
Orders
- Judgment entered for the claimant for £868,728.47 plus interest, fees, and costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment