VGC Construction Ltd v Jackson Civil Engineering Ltd [2008] EWHC 2082 (TCC) (15 August 2008)
The court held that the delay and disruption claim was not withdrawn or abandoned, was not so nebulous as to be incapable of giving rise to a dispute, and the adjudicator had jurisdiction to decide the dispute referred. The introduction of the Hudson formula calculation in the Reply did not deprive the adjudicator of jurisdiction, and there was no breach of natural justice.
- Citation
- [2008] EWHC 2082 (TCC)
- Parties
- Claimant: VGC Construction Limited; Defendant: Jackson Civil Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 15 August 2008
- Procedural Posture
- Summary Judgment Application for Enforcement of Adjudicator's Decision / High Court Judgment
- Outcome
- Summary judgment granted; adjudicator's decision enforced.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Delay and Disruption Claims, Extension of Time, Withdrawal of Claims, Natural Justice
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
VGC Construction Limited
Claimant
Jackson Civil Engineering Limited
Defendant
Procedural Posture
Summary Judgment Application for Enforcement of Adjudicator's Decision / High Court Judgment
Legal Issues
- 1 Whether the adjudicator had jurisdiction to decide the delay and disruption claim
- 2 Whether the delay and disruption claim was withdrawn or abandoned
- 3 Whether the claim was so nebulous and ill-defined as to be incapable of giving rise to a dispute
Ratio Decidendi
The court held that the delay and disruption claim was not withdrawn or abandoned, was not so nebulous as to be incapable of giving rise to a dispute, and the adjudicator had jurisdiction to decide the dispute referred. The introduction of the Hudson formula calculation in the Reply did not deprive the adjudicator of jurisdiction, and there was no breach of natural justice.
Court Disposition
Summary judgment granted; adjudicator's decision enforced.
Orders
- Jackson Civil Engineering Limited to pay VGC Construction Limited the sum determined by the adjudicator (£745,657.64)
- Jackson Civil Engineering Limited to pay the adjudicator's fees
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment