VGC Construction Ltd v Jackson Civil Engineering Ltd
The adjudicator had jurisdiction to decide the dispute regarding the final account, including the delay and disruption claim, as the claim was not withdrawn, was not so nebulous as to preclude a dispute, and the introduction of the Hudson formula calculation in the Reply did not deprive the adjudicator of jurisdiction. The respondent's submissions did not amount to a clear reservation of jurisdictional objection.
- Parties
- Claimant: VGC Construction Limited; Defendant: Jackson Civil Engineering Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 15 August 2008
- Procedural Posture
- Summary Judgment Application for Enforcement of Adjudicator's Decision / Judgment
- Outcome
- Judgment for the claimant; enforcement of adjudicator's decision upheld.
- Legal Topics
- Adjudication Enforcement, Jurisdiction of Adjudicator, Delay and Disruption Claims, Extension of Time, Summary Judgment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
VGC Construction Limited
Claimant
Jackson Civil Engineering Limited
Defendant
Procedural Posture
Summary Judgment Application for Enforcement of Adjudicator's Decision / Judgment
Legal Issues
- 1 Whether the adjudicator had jurisdiction to decide the delay and disruption claim
- 2 Whether the delay and disruption claim was withdrawn or held in abeyance
- 3 Whether the claim was so nebulous and ill-defined as to be incapable of giving rise to a dispute
Ratio Decidendi
The adjudicator had jurisdiction to decide the dispute regarding the final account, including the delay and disruption claim, as the claim was not withdrawn, was not so nebulous as to preclude a dispute, and the introduction of the Hudson formula calculation in the Reply did not deprive the adjudicator of jurisdiction. The respondent's submissions did not amount to a clear reservation of jurisdictional objection.
Court Disposition
Judgment for the claimant; enforcement of adjudicator's decision upheld.
Orders
- Judgment in favour of VGC Construction Limited for the sums claimed as per the adjudicator's decision.
- Jackson Civil Engineering Limited to pay the adjudicator's fees.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment