Pearce & High Ltd v Baxter & Anor [1999] EWCA Civ 789 (15 February 1999)
Clause 2.5 of the JCT Minor Works contract does not bar the employer from recovering damages for defects that became apparent during the defects liability period, even if notice was not given within that period; however, the employer's damages are limited to the cost the contractor would have incurred to remedy the...
Source-derived case information.
- Citation
- [1999] EWCA Civ 789
- Parties
- Respondent: Pearce & High Limited; Appellant: John P Baxter; Appellant: Mrs AS Baxter
- Jurisdiction
- England and Wales
- Judgment Date
- 15 February 1999
- Procedural Posture
- Appeal / Appeal From Swindon County Court, Judgment on Preliminary Issues
- Outcome
- Appeal allowed
- Legal Topics
- Defects Liability Period, Notice of Defects, Damages for Defective Works, Interpretation of JCT Contract Clauses
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Pearce & High Limited
Respondent
John P Baxter
Appellant
Mrs AS Baxter
Appellant
Procedural Posture
Appeal / Appeal From Swindon County Court, Judgment on Preliminary Issues
Legal Issues
- 1 Whether failure to notify defects within the defects liability period bars the employer from recovering damages for those defects
- 2 Interpretation of clause 2.5 of the JCT Minor Works contract regarding notice and remedy of defects
Ratio Decidendi
Clause 2.5 of the JCT Minor Works contract does not bar the employer from recovering damages for defects that became apparent during the defects liability period, even if notice was not given within that period; however, the employer's damages are limited to the cost the contractor would have incurred to remedy the defects, reflecting the employer's duty to mitigate loss.
Court Disposition
Appeal allowed
Orders
- Second issue (b) answered in the affirmative: employer is not barred from recovering damages for defects not notified within the defects liability period.
- Fourth issue (d) answered 'No': summary judgment for the contractor is not appropriate.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment