FT Everard & Sons Ltd. v Kent County Council

FT Everard & Sons Ltd. v Kent County Council

The defendant complied with its contractual obligations by commencing physical improvement works at the junction site prior to 31st December 1994, which were more than de minimis. Subsequent delays were caused by events beyond the defendant's reasonable control and did not constitute breach of the agreement. The...

Source-derived case information.

Parties
Claimant: F. T. Everard & Sons Limited; Defendant: Kent County Council
Jurisdiction
England and Wales
Judgment Date
04 October 2007
Procedural Posture
Civil / Judgment
Outcome
claim dismissed
Legal Topics
Interpretation of Contractual Obligations, Performance of Contract, Repayment of Contributions, Planning Agreements
Contract Law Interpretation of Contractual Obligations Performance of Contract Repayment of Contributions Planning Agreements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

F. T. Everard & Sons Limited

Claimant

Kent County Council

Defendant

Procedural Posture

Civil / Judgment

  1. 1 What were the defendant's obligations under the agreement dated 11th October 1988 regarding improvement works?
  2. 2 Did the defendant comply with its obligations to commence improvement works by 31st December 1994 under clause 16(5)?

Ratio Decidendi

The defendant complied with its contractual obligations by commencing physical improvement works at the junction site prior to 31st December 1994, which were more than de minimis. Subsequent delays were caused by events beyond the defendant's reasonable control and did not constitute breach of the agreement. The claimant's interpretation of the obligation to commence works was rejected.

Court Disposition

claim dismissed