Pharos Offshore Group Limited v Keynvor Morlift Limited
The contract provided for indicative daily rates and not a capped number of days; waiting on weather remained KML's risk; Pharos was not in breach for customs delays as no actual delay was caused; ancillary equipment supplied by Pharos was sub-standard, causing excessive downtime, for which Pharos was liable; Pharos was entitled to payment for the reasonable period of works, including weather downtime, but not for periods prior to arrival of equipment or for breakdowns caused by its breach; KML was not entitled to liquidated damages as no fixed completion date was specified; KML was entitled to set-off for 8 days of culpable delay caused by Pharos's breaches.
- Parties
- Claimant: Pharos Offshore Group Limited; Defendant: Keynvor Morlift Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 07 November 2025
- Procedural Posture
- Commercial Contract Dispute / Final Judgment
- Outcome
- Judgment for Claimant with set-off for Defendant's counterclaim
- Legal Topics
- Contract Interpretation, Implied Terms, Fitness for Purpose, Delay and Damages, Set Off, Supply of Goods and Services Act 1982
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Pharos Offshore Group Limited
Claimant
Keynvor Morlift Limited
Defendant
Procedural Posture
Commercial Contract Dispute / Final Judgment
Legal Issues
- 1 Whether Pharos was entitled to claim daily charges for more than 10 days
- 2 Whether Pharos was entitled to claim for more than 7 personnel per day
- 3 Whether Pharos was entitled to claim for personnel prior to arrival of UTV-670
Ratio Decidendi
The contract provided for indicative daily rates and not a capped number of days; waiting on weather remained KML's risk; Pharos was not in breach for customs delays as no actual delay was caused; ancillary equipment supplied by Pharos was sub-standard, causing excessive downtime, for which Pharos was liable; Pharos was entitled to payment for the reasonable period of works, including weather downtime, but not for periods prior to arrival of equipment or for breakdowns caused by its breach; KML was not entitled to liquidated damages as no fixed completion date was specified; KML was entitled to set-off for 8 days of culpable delay caused by Pharos's breaches.
Court Disposition
Judgment for Claimant with set-off for Defendant's counterclaim
Orders
- Pharos is owed £507,402.76 plus VAT (£608,883.31 inclusive of VAT)
- KML's counterclaim for damages succeeds in the sum of £113,214.63, to be set off against sums owed to Pharos
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment