Joinery Plus Ltd (In Administration) v Laing Ltd
The adjudicator's decision was a nullity because it was made by reference to the wrong contract conditions (JCT Works Contract instead of DOM/2 DOM/2 conditions), failed to answer the question referred, and applied inapplicable provisions. The errors were fundamental, went to jurisdiction, and were incapable of correction. Joinery did not affirm the decision by accepting payment, as it was accepted on account with reservation of rights. Joinery is entitled to refer the dispute to a new adjudication, and Laing is not entitled to repayment as a precondition or by counterclaim, given Joinery's equitable set-off and administration status.
- Parties
- Claimant: Joinery Plus Limited (in administration); Defendant: Laing Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 16 January 2003
- Procedural Posture
- Civil / Judgment
- Outcome
- Declaration granted; adjudicator's decision declared a nullity; Joinery entitled to fresh adjudication; Laing's application for repayment refused.
- Legal Topics
- Adjudication, Jurisdiction, Restitution, Insolvency, Declaratory Relief
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Joinery Plus Limited (in administration)
Claimant
Laing Limited
Defendant
Procedural Posture
Civil / Judgment
Legal Issues
- 1 Whether the adjudicator's decision dated 6 August 2001 was a nullity for being made under the wrong contract conditions
- 2 Whether Joinery affirmed the adjudicator's decision by accepting payment
- 3 Whether Joinery may start a fresh adjudication on the same disputes
Ratio Decidendi
The adjudicator's decision was a nullity because it was made by reference to the wrong contract conditions (JCT Works Contract instead of DOM/2 DOM/2 conditions), failed to answer the question referred, and applied inapplicable provisions. The errors were fundamental, went to jurisdiction, and were incapable of correction. Joinery did not affirm the decision by accepting payment, as it was accepted on account with reservation of rights. Joinery is entitled to refer the dispute to a new adjudication, and Laing is not entitled to repayment as a precondition or by counterclaim, given Joinery's equitable set-off and administration status.
Court Disposition
Declaration granted; adjudicator's decision declared a nullity; Joinery entitled to fresh adjudication; Laing's application for repayment refused.
Orders
- The adjudicator's decision dated 6 August 2001 is a nullity and given without jurisdiction.
- Joinery may serve a new Notice of Adjudication regarding the Stakis London Metropole Hotel subcontract.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment