Haberdashers' Aske's Federation Trust Ltd v Lakehouse Contracts Ltd & Ors [2018] EWHC 558 (TCC) (19 March 2018)
Where a subcontract expressly requires the subcontractor to obtain its own insurance, the subcontractor is not entitled to the benefit of project-wide insurance as a co-insured, and project insurers may pursue a subrogated claim against the subcontractor to the extent of its own insurance cover.
- Citation
- [2018] EWHC 558 (TCC)
- Parties
- Claimant: Haberdashers' Aske's Federation Trust Limited; Claimant: The Mayor and Burgesses of the London Borough of Lewisham; Defendant: Lakehouse Contracts Limited; Defendant: Cambridge Polymer Roofing Limited; Third Party: Zurich Insurance plc; Third Party: QBE Casualty Syndicate 386; Third Party: CNA Insurance Company Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 19 March 2018
- Procedural Posture
- Commercial Construction Insurance Dispute / Judgment on Preliminary Issues
- Outcome
- Declaration refused; CPR not entitled to benefit of Project Insurance as co-insured.
- Legal Topics
- Project Insurance, Co Insureds, Subrogation, Construction Contracts, Third Party Rights, Implied Terms
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Haberdashers' Aske's Federation Trust Limited
Claimant
The Mayor and Burgesses of the London Borough of Lewisham
Claimant
Lakehouse Contracts Limited
Defendant
Cambridge Polymer Roofing Limited
Defendant
Zurich Insurance plc
Third Party
QBE Casualty Syndicate 386
Third Party
CNA Insurance Company Limited
Third Party
Procedural Posture
Commercial Construction Insurance Dispute / Judgment on Preliminary Issues
Legal Issues
- 1 Whether CPR is entitled to the benefit of project-wide insurance as a co-insured despite an express term requiring its own insurance
- 2 Whether project insurers can pursue a subrogated claim against CPR for losses covered by CPR's own insurance
- 3 Legal mechanism by which subcontractors become co-insureds under project insurance
Ratio Decidendi
Where a subcontract expressly requires the subcontractor to obtain its own insurance, the subcontractor is not entitled to the benefit of project-wide insurance as a co-insured, and project insurers may pursue a subrogated claim against the subcontractor to the extent of its own insurance cover.
Court Disposition
Declaration refused; CPR not entitled to benefit of Project Insurance as co-insured.
Orders
- CPR's application for a declaration is dismissed.
- Project Insurers may pursue a subrogated claim against CPR up to the limit of its own insurance.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment