Redrow Homes Ltd v Martin Dawn (Leckhampton) Ltd
The defendant's obligation under clause 15.9 of the legal charge to execute the section 106 agreement is unqualified (save for the express proviso) and is not rendered inequitable by the claimant's arguable breaches of contract, which sound only in damages. The breaches are not sufficiently connected to the obligation sought to be enforced to justify refusing specific performance. The defendant remains adequately secured and can pursue damages if so advised.
- Parties
- Claimant: Redrow Homes Limited; Defendant: Martin Dawn (Leckhampton) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 13 April 2016
- Procedural Posture
- Civil (chancery Division) / Summary Judgment Application
- Outcome
- Summary judgment granted for specific performance
- Legal Topics
- Specific Performance, Legal Charge, Section 106 Agreement, Summary Judgment, Breach of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Redrow Homes Limited
Claimant
Martin Dawn (Leckhampton) Limited
Defendant
Procedural Posture
Civil (chancery Division) / Summary Judgment Application
Legal Issues
- 1 Whether the defendant is obliged to execute a section 106 agreement under clause 15.9 of the legal charge
- 2 Whether alleged breaches by the claimant disentitle it to specific performance
- 3 Whether the defendant's claims for damages are a defence to specific performance
Ratio Decidendi
The defendant's obligation under clause 15.9 of the legal charge to execute the section 106 agreement is unqualified (save for the express proviso) and is not rendered inequitable by the claimant's arguable breaches of contract, which sound only in damages. The breaches are not sufficiently connected to the obligation sought to be enforced to justify refusing specific performance. The defendant remains adequately secured and can pursue damages if so advised.
Court Disposition
Summary judgment granted for specific performance
Orders
- Defendant ordered to execute and deliver the Tewkesbury Borough Council section 106 agreement forthwith
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment