Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd
MMT was not in repudiatory breach as of 17 February 2015; ICI was in repudiatory breach by instructing MMT to leave site. The contract required only dye-penetration NDT, not radiography. None of the five pleaded breaches by MMT were made out. ICI is entitled to recover any overpayment under the contract, not by restitution, but restitution would be available if not. Damages for defective work are limited to the cost to MMT of rectification. MMT is entitled to damages for ICI's repudiation. ICI's claim for project documents is moot as they were provided; no damages for late delivery are established.
- Parties
- Claimant: Imperial Chemical Industries Limited; Defendant: Merit Merrell Technology Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 12 July 2017
- Procedural Posture
- Civil (construction Contract Dispute) / Judgment After Split Trial on Liability
- Outcome
- Judgment for the Defendant (MMT) on liability; Claimant (ICI) found to have repudiated the contract; directions to be made for quantum trial.
- Legal Topics
- Repudiation of Contract, Defective Work, Non Destructive Testing (ndt), Project Documentation, Damages for Breach of Contract, Restitution, Role of Project Manager, Adjudication Enforcement
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Imperial Chemical Industries Limited
Claimant
Merit Merrell Technology Limited
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Judgment After Split Trial on Liability
Legal Issues
- 1 Whether the defendant was in repudiatory breach of contract as of 17 February 2015
- 2 Whether the claimant was in repudiatory breach by instructing the defendant to leave site
- 3 Whether the contract required radiographic NDT or only dye-penetration testing
Ratio Decidendi
MMT was not in repudiatory breach as of 17 February 2015; ICI was in repudiatory breach by instructing MMT to leave site. The contract required only dye-penetration NDT, not radiography. None of the five pleaded breaches by MMT were made out. ICI is entitled to recover any overpayment under the contract, not by restitution, but restitution would be available if not. Damages for defective work are limited to the cost to MMT of rectification. MMT is entitled to damages for ICI's repudiation. ICI's claim for project documents is moot as they were provided; no damages for late delivery are established.
Court Disposition
Judgment for the Defendant (MMT) on liability; Claimant (ICI) found to have repudiated the contract; directions to be made for quantum trial.
Orders
- All pleaded repudiatory breaches by MMT dismissed.
- ICI's claim for contractual termination dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment