Imperial Chemical Industries Ltd v Merit Merrell Technology Ltd
The court found that ICI was not entitled to revisit or ignore contemporaneous agreements and assessments reached with MMT and the Project Manager regarding the value of works, rates, and measures. The burden of proof was on ICI to demonstrate overpayment, which it failed to do. The vast majority of ICI’s challenges were unsupported by direct evidence or contractual basis. The correct valuation of MMT’s works was determined by reference to the agreed rates, measures, and contemporaneous agreements, with only minor adjustments. Damages for repudiatory breach were awarded for professional fees, management time, and certain consequential losses, but not for liquidation costs or speculative...
- Parties
- Claimant: Imperial Chemical Industries Limited; Defendant: Merit Merrell Technology Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 21 June 2018
- Procedural Posture
- Civil (construction Contract Dispute) / Quantum Judgment (following Liability Judgment)
- Outcome
- Judgment for the Defendant (MMT) on both the final account and counterclaim; ICI’s claim for overpayment dismissed.
- Legal Topics
- Repudiatory Breach, Quantum Meruit, Damages, Adjudication Enforcement, Burden of Proof, Contractual Interpretation, Estoppel, Expert Evidence
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Imperial Chemical Industries Limited
Claimant
Merit Merrell Technology Limited
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Quantum Judgment (following Liability Judgment)
Legal Issues
- 1 What is the value of the work carried out by MMT as at 17 February 2015?
- 2 What damages is MMT entitled to recover as a result of ICI’s repudiatory breach of contract?
- 3 How should preliminaries, PMIs, SIs, and other claims be valued under the contract?
Ratio Decidendi
The court found that ICI was not entitled to revisit or ignore contemporaneous agreements and assessments reached with MMT and the Project Manager regarding the value of works, rates, and measures. The burden of proof was on ICI to demonstrate overpayment, which it failed to do. The vast majority of ICI’s challenges were unsupported by direct evidence or contractual basis. The correct valuation of MMT’s works was determined by reference to the agreed rates, measures, and contemporaneous agreements, with only minor adjustments. Damages for repudiatory breach were awarded for professional fees, management time, and certain consequential losses, but not for liquidation costs or speculative...
Court Disposition
Judgment for the Defendant (MMT) on both the final account and counterclaim; ICI’s claim for overpayment dismissed.
Orders
- ICI to pay MMT £2,128,094.78 (net of all set-offs and counterclaims)
- Interest to be calculated as per agreement or further order
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment