Jordan v MGN Ltd [2017] EWHC 1937 (Ch) (24 July 2017)
The court held that there was no binding agreement on damages between the parties; the only agreement was on the amount offered in settlement negotiations, not as a resolution of the claim. The claimant's late acceptance of the September 2014 Part 36 offer, after incurring significant additional costs and failing to engage constructively in settlement, meant the normal costs consequences under CPR 36.10(5) should apply. The claimant was responsible for the unnecessary costs incurred after the expiry of the relevant period. The court found no basis to depart from the normal rule, and the defendant was entitled to its costs for the relevant period on the standard basis, not indemnity.
- Citation
- [2017] EWHC 1937 (Ch)
- Parties
- Claimant: Edmund Patrick Jordan; Defendant: MGN Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 24 July 2017
- Procedural Posture
- Civil / Post Application, Pre Trial; Determination of Costs Following Late Acceptance of Part 36 Offer
- Outcome
- Application dismissed; normal costs consequences of late acceptance of Part 36 offer apply.
- Legal Topics
- Part 36 Offers, Costs Consequences, Abuse of Process, Settlement Negotiations, Phone Hacking, Conditional Fee Agreements
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Edmund Patrick Jordan
Claimant
MGN Limited
Defendant
Procedural Posture
Civil / Post Application, Pre Trial; Determination of Costs Following Late Acceptance of Part 36 Offer
Legal Issues
- 1 Whether the claimant is entitled to costs after late acceptance of a Part 36 offer
- 2 Whether the normal costs consequences under CPR 36.10(5) should be departed from
- 3 Whether the defendant is entitled to indemnity costs for the relevant period
Ratio Decidendi
The court held that there was no binding agreement on damages between the parties; the only agreement was on the amount offered in settlement negotiations, not as a resolution of the claim. The claimant's late acceptance of the September 2014 Part 36 offer, after incurring significant additional costs and failing to engage constructively in settlement, meant the normal costs consequences under CPR 36.10(5) should apply. The claimant was responsible for the unnecessary costs incurred after the expiry of the relevant period. The court found no basis to depart from the normal rule, and the defendant was entitled to its costs for the relevant period on the standard basis, not indemnity.
Court Disposition
Application dismissed; normal costs consequences of late acceptance of Part 36 offer apply.
Orders
- Claimant to pay defendant's costs from 15 September 2016 to date of acceptance of the September 2014 Part 36 offer, on the standard basis.
- No order for indemnity costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment