Vitpol Building Service v Samen

Vitpol Building Service v Samen

The Technology and Construction Court has jurisdiction to determine the existence and terms of the contract even though adjudication has not commenced, and Part 8 proceedings are appropriate unless significant factual disputes requiring oral evidence arise.

Parties
Claimant: Vitpol Building Service; Defendant: Michael Samen
Jurisdiction
England and Wales
Judgment Date
16 September 2008
Procedural Posture
Civil / Case Management Conference
Outcome
Court affirms jurisdiction and will make directions for resolution of contractual issues.
Legal Topics
Existence of Contract, Contract Terms, Jurisdiction, Adjudication Rights, Procedure Under Part 8

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 4 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Vitpol Building Service

Claimant

Michael Samen

Defendant

Procedural Posture

Civil / Case Management Conference

  1. 1 Does the court have jurisdiction to determine the existence and/or terms of a contract where adjudication has not yet commenced?
  2. 2 Is Part 8 procedure appropriate given the factual disputes regarding the contract?

Ratio Decidendi

The Technology and Construction Court has jurisdiction to determine the existence and terms of the contract even though adjudication has not commenced, and Part 8 proceedings are appropriate unless significant factual disputes requiring oral evidence arise.

Court Disposition

Court affirms jurisdiction and will make directions for resolution of contractual issues.

Orders

  • Directions to resolve contractual issues to be made after the pre-action protocol meeting.
  • Timetable to be set for speedy resolution, allowing defendant proper time to prepare evidence.