Husband and Brown Ltd v Mitch Developments Ltd

Husband and Brown Ltd v Mitch Developments Ltd

The negotiations for the Site were a single transaction, and the Claimant is entitled to an incentive fee of 25% of the saving between the original offer (£500,007) and the final purchase price (£325,000). The agreement was not a construction contract under the 1996 Act, and adjudication and legal costs are not recoverable.

Parties
Claimant: Husband and Brown Limited; Defendant: Mitch Developments Limited
Jurisdiction
England and Wales
Judgment Date
16 October 2015
Procedural Posture
Civil (commercial) / Judgment After Trial
Outcome
Claim for incentive fee succeeds; claim for adjudication and legal costs dismissed; counterclaim for declaration dismissed; proceedings stayed by Tomlin order on settlement terms.
Legal Topics
Oral Agreements, Incentive Fees, Construction Contracts, Adjudication Costs, Interpretation of Contracts

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Husband and Brown Limited

Claimant

Mitch Developments Limited

Defendant

Procedural Posture

Civil (commercial) / Judgment After Trial

  1. 1 Whether the Claimant is entitled to an incentive fee based on the reduction from the initial agreed offer to the price paid on completion for the Site
  2. 2 Whether the agreement between the parties was a construction contract within the meaning of the Housing Grants Construction and Regeneration Act 1996
  3. 3 Whether adjudication and legal costs are recoverable by the Claimant

Ratio Decidendi

The negotiations for the Site were a single transaction, and the Claimant is entitled to an incentive fee of 25% of the saving between the original offer (£500,007) and the final purchase price (£325,000). The agreement was not a construction contract under the 1996 Act, and adjudication and legal costs are not recoverable.

Court Disposition

Claim for incentive fee succeeds; claim for adjudication and legal costs dismissed; counterclaim for declaration dismissed; proceedings stayed by Tomlin order on settlement terms.

Orders

  • Claimant entitled to incentive fee of 25% of the saving between £500,007 and £325,000
  • Claim for adjudication and legal costs dismissed