West 3 Mechanical Contractors Ltd v Mizen Design Build Ltd [2013] EWHC 4004 (TCC) (13 December 2013)
West 3's contractual obligation was to install 1 inch TracPipe as the gas distribution pipe from the gas meter room to the flats, as specified in the agreement and confirmed by incorporated correspondence. West 3 had no design responsibility for pipe sizing or compliance with the 1 mbar pressure drop requirement. No effective contractual variation occurred because the procedures in Clause 8.1 were not followed and revised drawings were not properly issued or agreed as variations. Responsibility for the gas pressure defect did not rest with West 3 under the contract.
- Citation
- [2013] EWHC 4004 (TCC)
- Parties
- Claimant: West 3 Mechanical Contractors Limited; Defendant: Mizen Design Build Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 13 December 2013
- Procedural Posture
- Preliminary Issue Trial (tcc) / Judgment After Trial of Preliminary Issue
- Outcome
- West 3 not liable for gas pressure defect; no breach of contractual obligation found.
- Legal Topics
- Subcontractor Obligations, Variation of Contract, Interpretation of Construction Contracts, Design Responsibility, Remedial Works Liability
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
West 3 Mechanical Contractors Limited
Claimant
Mizen Design Build Limited
Defendant
Procedural Posture
Preliminary Issue Trial (tcc) / Judgment After Trial of Preliminary Issue
Legal Issues
- 1 What was West 3's contractual obligation under the Agreement as regards the size of the gas pipework?
- 2 Was the original contractual obligation ever effectively varied and, if so, what was the effect of any such variation?
- 3 Did the system as originally installed fail to deliver sufficient gas pressure to a substantial number of flats and would the system in the revised drawings have delivered adequate gas pressures to all the flats?
Ratio Decidendi
West 3's contractual obligation was to install 1 inch TracPipe as the gas distribution pipe from the gas meter room to the flats, as specified in the agreement and confirmed by incorporated correspondence. West 3 had no design responsibility for pipe sizing or compliance with the 1 mbar pressure drop requirement. No effective contractual variation occurred because the procedures in Clause 8.1 were not followed and revised drawings were not properly issued or agreed as variations. Responsibility for the gas pressure defect did not rest with West 3 under the contract.
Court Disposition
West 3 not liable for gas pressure defect; no breach of contractual obligation found.
Orders
- Declaration that West 3's obligation was limited to installing 1 inch TracPipe as specified.
- No liability attaches to West 3 for the gas pressure defect under the contract.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment