Balfour Beatty Construction Northern Ltd v Modus Corovest (Blackpool) Ltd [2008] EWHC 3029 (TCC) (04 December 2008)
The adjudicator's decision was valid and reasoned, and must be enforced. The sum certified under interim certificate 29 is due as no withholding notice was served. Modus cannot set off its counterclaim for liquidated damages against sums due to Balfour Beatty. There is no realistic prospect of a defence to the claims, and summary judgment is granted.
- Citation
- [2008] EWHC 3029 (TCC)
- Parties
- Claimant: Balfour Beatty Construction Northern Limited; Defendant: Modus Corovest (Blackpool) Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 04 December 2008
- Procedural Posture
- Commercial Construction Dispute / Summary Judgment Application
- Outcome
- Summary judgment granted for claimant; defendant's applications refused.
- Legal Topics
- Adjudication Enforcement, Summary Judgment, Interim Payments, Liquidated Damages, Set Off, Mediation Clauses
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Balfour Beatty Construction Northern Limited
Claimant
Modus Corovest (Blackpool) Ltd
Defendant
Procedural Posture
Commercial Construction Dispute / Summary Judgment Application
Legal Issues
- 1 Whether the adjudicator's decision should be enforced by summary judgment
- 2 Whether the claimant is entitled to payment under interim certificate 29
- 3 Whether the defendant can set off or counterclaim for liquidated damages
Ratio Decidendi
The adjudicator's decision was valid and reasoned, and must be enforced. The sum certified under interim certificate 29 is due as no withholding notice was served. Modus cannot set off its counterclaim for liquidated damages against sums due to Balfour Beatty. There is no realistic prospect of a defence to the claims, and summary judgment is granted.
Court Disposition
Summary judgment granted for claimant; defendant's applications refused.
Orders
- Judgment for Balfour Beatty in the sum of £183,492 (adjudicator's decision plus interest)
- Judgment for Balfour Beatty in the sum of £994,988 (interim certificate 29 plus interest)
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment