Trident House Development Limited v Mohammed Yousaf
Trident failed to prove on the balance of probabilities that Mr Yousaf's admitted trespass and nuisance caused any delay to the completion of the Galem House project; contemporaneous project records and witness evidence did not establish causation. However, the works for which access was sought constituted renewal reasonably necessary for preservation, and the formation of windows was an incidental alteration. An access order was therefore granted, with privilege consideration set at £3,500, reflecting the limited inconvenience to Mr Yousaf and the broader public interest in the redevelopment.
- Parties
- Claimant: Trident House Development Limited; Defendant: Mohammed Yousaf
- Jurisdiction
- England and Wales
- Judgment Date
- 21 February 2025
- Procedural Posture
- Civil (property, Trusts, and Probate) / Final Judgment After Trial of Damages Claim (causation Only) and Final Hearing of Access Claim
- Outcome
- Damages Claim dismissed; Access Claim allowed with access order granted and consideration ordered.
- Legal Topics
- Trespass, Nuisance, Access to Neighbouring Land, Damages—causation, Injunctions, Planning Permission, Renewal and Repair, Consideration Under Access Orders
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Trident House Development Limited
Claimant
Mohammed Yousaf
Defendant
Procedural Posture
Civil (property, Trusts, and Probate) / Final Judgment After Trial of Damages Claim (causation Only) and Final Hearing of Access Claim
Legal Issues
- 1 Whether the defendant's tortious conduct caused delay to the claimant's project and, if so, by how long (Damages Claim)
- 2 Whether an access order should be made under the Access to Neighbouring Land Act 1992 (Access Claim)
- 3 Whether and what consideration should be payable for access under s.2(5) of the 1992 Act
Ratio Decidendi
Trident failed to prove on the balance of probabilities that Mr Yousaf's admitted trespass and nuisance caused any delay to the completion of the Galem House project; contemporaneous project records and witness evidence did not establish causation. However, the works for which access was sought constituted renewal reasonably necessary for preservation, and the formation of windows was an incidental alteration. An access order was therefore granted, with privilege consideration set at £3,500, reflecting the limited inconvenience to Mr Yousaf and the broader public interest in the redevelopment.
Court Disposition
Damages Claim dismissed; Access Claim allowed with access order granted and consideration ordered.
Orders
- Damages Claim dismissed for lack of causation.
- Access order granted in agreed terms for works to Galem House wall, including formation of windows.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment