Hescorp Italia SpA v. Morrison Construction Ltd, Impregilo UK Ltd [2000] EWHC Technology 123 (17th March, 2000)
No contract was formed as the parties failed to agree on essential terms, specifically the completion date and measure of liquidated damages; therefore, the Claimant is entitled to payment for its work on a quantum meruit basis.
- Citation
- [2000] EWHC Technology 123
- Parties
- Claimant: Hescorp Italia SpA (formerly Imprefeal SpA); Defendant: Morrison-Impregilo Coventry Construction Joint Venture (First Defendant); Defendant: Morrison-Impregilo Coventry Construction Joint Venture (Second Defendant)
- Jurisdiction
- England and Wales
- Procedural Posture
- Construction Contract Dispute / Application for Summary Judgment And/or Interim Payment
- Outcome
- Applications for summary judgment and interim payment adjourned; no contract found; Claimant entitled to quantum meruit, amount to be assessed.
- Legal Topics
- Contract Formation, Quantum Meruit, Summary Judgment, Liquidated Damages, Authority of Agents
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hescorp Italia SpA (formerly Imprefeal SpA)
Claimant
Morrison-Impregilo Coventry Construction Joint Venture (First Defendant)
Defendant
Morrison-Impregilo Coventry Construction Joint Venture (Second Defendant)
Defendant
Procedural Posture
Construction Contract Dispute / Application for Summary Judgment And/or Interim Payment
Legal Issues
- 1 Whether a binding contract was formed between the parties
- 2 Whether essential terms (completion date and liquidated damages) were agreed
- 3 Effect of requirement for contract to be executed as a deed
Ratio Decidendi
No contract was formed as the parties failed to agree on essential terms, specifically the completion date and measure of liquidated damages; therefore, the Claimant is entitled to payment for its work on a quantum meruit basis.
Court Disposition
Applications for summary judgment and interim payment adjourned; no contract found; Claimant entitled to quantum meruit, amount to be assessed.
Orders
- Application for summary judgment adjourned for further argument.
- Application for interim payment adjourned.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment