Monavon Construction Ltd v Davenport & Anor
There was no enforceable cost ceiling due to lack of definition and certainty in the oral agreement. Monavon was liable for specific defects and omissions where it failed to meet contractual obligations, including failure to test and remedy electrical works, improper installation of heating, and inadequate damp proofing. Damages were awarded for proven defects and incomplete works, while claims not substantiated or outside Monavon's responsibility were dismissed.
- Parties
- Claimant: Monavon Construction Limited; Defendant: Mr Simon Davenport; Defendant: Mrs Angelika Davenport
- Jurisdiction
- England and Wales
- Judgment Date
- 22 May 2006
- Procedural Posture
- Civil / Judgment After Trial
- Outcome
- Judgment for both parties in part; net judgment to be ascertained based on findings; damages awarded for proven defects and incomplete works; some claims dismissed.
- Legal Topics
- Building Contracts, Oral Agreements, Breach of Contract, Damages, Defective Workmanship
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Monavon Construction Limited
Claimant
Mr Simon Davenport
Defendant
Mrs Angelika Davenport
Defendant
Procedural Posture
Civil / Judgment After Trial
Legal Issues
- 1 Whether there was a binding cost ceiling in the oral contract
- 2 Whether Monavon was liable for defective works and omissions
- 3 Whether the Davenports were entitled to damages for specific defects and incomplete works
Ratio Decidendi
There was no enforceable cost ceiling due to lack of definition and certainty in the oral agreement. Monavon was liable for specific defects and omissions where it failed to meet contractual obligations, including failure to test and remedy electrical works, improper installation of heating, and inadequate damp proofing. Damages were awarded for proven defects and incomplete works, while claims not substantiated or outside Monavon's responsibility were dismissed.
Court Disposition
Judgment for both parties in part; net judgment to be ascertained based on findings; damages awarded for proven defects and incomplete works; some claims dismissed.
Orders
- Parties to calculate net judgment in accordance with findings.
- Court to enter judgment for the ascertained sum and consider interest and costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment