Willow Corp S.À.R.L. v MTD Contractors Ltd [2019] EWHC 1591 (TCC) (25 June 2019)
The June 2017 agreement did not require Willow to accept Practical Completion simply upon agreement of a list of outstanding works; MTD was required to achieve Practical Completion by 28 July 2017 except for specified works. The adjudicator erred in his construction of the agreement, but there was no significant breach of natural justice. The adjudicator's decision is enforceable, subject to severance if necessary.
- Citation
- [2019] EWHC 1591 (TCC)
- Parties
- Claimant: Willow Corp S.À. R. L.; Defendant: MTD Contractors Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 25 June 2019
- Procedural Posture
- Civil (technology and Construction Court) / Judgment on Part 8 Claim for Declaratory Relief and Part 7 Claim for Summary Judgment Enforcement of Adjudication
- Outcome
- Summary judgment granted in favour of MTD Contractors Limited; Willow's Part 8 claim for declaratory relief dismissed.
- Legal Topics
- Adjudication Enforcement, Contract Interpretation, Natural Justice in Adjudication, Summary Judgment, Severance of Adjudicator's Decision
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Willow Corp S.À. R. L.
Claimant
MTD Contractors Limited
Defendant
Procedural Posture
Civil (technology and Construction Court) / Judgment on Part 8 Claim for Declaratory Relief and Part 7 Claim for Summary Judgment Enforcement of Adjudication
Legal Issues
- 1 Proper construction of the June 2017 supplementary agreement regarding Practical Completion and liquidated damages
- 2 Whether the adjudicator's decision is unenforceable due to alleged breaches of natural justice
- 3 Whether the adjudicator's decision can be severed if partially invalid
Ratio Decidendi
The June 2017 agreement did not require Willow to accept Practical Completion simply upon agreement of a list of outstanding works; MTD was required to achieve Practical Completion by 28 July 2017 except for specified works. The adjudicator erred in his construction of the agreement, but there was no significant breach of natural justice. The adjudicator's decision is enforceable, subject to severance if necessary.
Court Disposition
Summary judgment granted in favour of MTD Contractors Limited; Willow's Part 8 claim for declaratory relief dismissed.
Orders
- Willow to pay MTD the sum of £1,174,854.92 plus VAT and interest of £36,294.84 as ordered by the adjudicator.
- Willow's application for declaratory relief is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment