Honeywell Control Systems Ltd. v Multiplex Constructions (UK) Ltd.
The right to inspect the main contract under the sub-contract is a continuing operative provision, not limited to pre-contract, and extends to those parts of the Settlement Agreement which vary the main contract. However, the right is limited to inspection at the contractor's offices and does not include a right to take or receive copies.
- Parties
- Claimant: Honeywell Control Systems Limited; Defendant: Multiplex Constructions (UK) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 27 February 2007
- Procedural Posture
- Civil (construction Contract Dispute) / Judgment After Trial of Claim for Declarations and Specific Performance
- Outcome
- Claim allowed in part
- Legal Topics
- Right to Inspect Contract Documents, Variation of Contract, Specific Performance, Confidentiality
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Honeywell Control Systems Limited
Claimant
Multiplex Constructions (UK) Limited
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Judgment After Trial of Claim for Declarations and Specific Performance
Legal Issues
- 1 Does Honeywell have a continuing right to inspect the main contract under the sub-contract?
- 2 Does that right extend to the Settlement Agreement?
- 3 Is Honeywell entitled to obtain copies of the Settlement Agreement?
Ratio Decidendi
The right to inspect the main contract under the sub-contract is a continuing operative provision, not limited to pre-contract, and extends to those parts of the Settlement Agreement which vary the main contract. However, the right is limited to inspection at the contractor's offices and does not include a right to take or receive copies.
Court Disposition
Claim allowed in part
Orders
- Declarations granted that Honeywell has a continuing right to inspect the main contract and to inspect those parts of the Settlement Agreement which vary the main contract, but not to take copies.
- Order for specific performance requiring Multiplex to permit Honeywell to view an appropriately redacted version of the Settlement Agreement.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment