Energy Works (Hull) Ltd v MW High Tech Projects UK Ltd & Anor (Judgment No. 2) [2023] EWHC 1142 (TCC) (12 May 2023)
The settlement between the employer and main contractor does not preclude the main contractor from pursuing contribution claims or abatement against the subcontractor, provided the main contractor proves the subcontractor’s liability for the same damage. Contribution is assessed on a just and equitable basis, and notification requirements under the subcontract are strictly enforced. Abatement remains available as a defence to the subcontract price for defective works. Subcontractor's claims for variations fail where contractual requirements for instruction and notification are not met.
- Citation
- [2023] EWHC 1142 (TCC)
- Parties
- Claimant: Energy Works (Hull) Limited; Defendant: MW High Tech Projects UK Limited; Defendant: M+W Group GmbH; Third Party: Outotec (USA) Inc.
- Jurisdiction
- England and Wales
- Judgment Date
- 12 May 2023
- Procedural Posture
- Technology and Construction Court Litigation / Post Trial Judgment on Outstanding Issues Between Main Contractor and Subcontractor
- Outcome
- M+W’s contribution claim against Outotec succeeds in part (defect 7: ladders, £20,000); all other contribution claims dismissed for want of notification or lack of evidence. Outotec’s claims for variations are dismissed. M+W’s defence of abatement succeeds in the sum of $488,746.65. Construction of enhanced interest...
- Legal Topics
- Contribution Claims, Abatement, Defective Works, Settlement Agreements, Contractual Variations, Notification Requirements
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Energy Works (Hull) Limited
Claimant
MW High Tech Projects UK Limited
Defendant
M+W Group GmbH
Defendant
Outotec (USA) Inc.
Third Party
Procedural Posture
Technology and Construction Court Litigation / Post Trial Judgment on Outstanding Issues Between Main Contractor and Subcontractor
Legal Issues
- 1 Whether settlement between employer and main contractor precludes contribution claims or abatement by main contractor against subcontractor
- 2 Assessment of contribution claims for specific defects
- 3 Entitlement to abatement for defects in subcontract works
Ratio Decidendi
The settlement between the employer and main contractor does not preclude the main contractor from pursuing contribution claims or abatement against the subcontractor, provided the main contractor proves the subcontractor’s liability for the same damage. Contribution is assessed on a just and equitable basis, and notification requirements under the subcontract are strictly enforced. Abatement remains available as a defence to the subcontract price for defective works. Subcontractor's claims for variations fail where contractual requirements for instruction and notification are not met.
Court Disposition
M+W’s contribution claim against Outotec succeeds in part (defect 7: ladders, £20,000); all other contribution claims dismissed for want of notification or lack of evidence. Outotec’s claims for variations are dismissed. M+W’s defence of abatement succeeds in the sum of $488,746.65. Construction of enhanced interest...
Orders
- Outotec to pay M+W £20,000 as contribution for defect 7 (ladders)
- All other contribution claims by M+W against Outotec dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment