Energy Works (Hull) Ltd v MW High Tech Projects UK Ltd & Ors [2022] EWHC 3275 (TCC) (20 December 2022)
EWH was entitled to terminate the EPC contract for contractor's default and repudiation as M+W was not entitled to an extension of time. M+W's allegations of breach by EWH were either not established or did not cause delay. EWH is entitled to liquidated damages, termination damages, and defect damages. M+W Group GmbH is liable under the parent company guarantee. M+W's counterclaim is dismissed. Outotec's liability for defects is limited to properly notified matters; most contribution claims fail except for defect 17. Outotec is entitled to milestone payments subject to abatement.
- Citation
- [2022] EWHC 3275 (TCC)
- Parties
- Claimant: Energy Works (Hull) Limited; Defendant: MW High Tech Projects UK Limited; Defendant: M+W Group GmbH; Third Party: Outotec (USA) Inc.
- Jurisdiction
- England and Wales
- Judgment Date
- 20 December 2022
- Procedural Posture
- Commercial Construction Dispute / Final Judgment (liability and Quantum)
- Outcome
- Claimant succeeds in main claims; Defendants' counterclaims mostly dismissed; Third Party partially succeeds in counterclaim for milestone payments.
- Legal Topics
- EPC Contracts, Termination for Default, Extension of Time, Liquidated Damages, Defects Liability, Parent Company Guarantee, Contribution Claims, Abatement, Contractual Interpretation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Energy Works (Hull) Limited
Claimant
MW High Tech Projects UK Limited
Defendant
M+W Group GmbH
Defendant
Outotec (USA) Inc.
Third Party
Procedural Posture
Commercial Construction Dispute / Final Judgment (liability and Quantum)
Legal Issues
- 1 Was EWH entitled to terminate the EPC contract for contractor's default or repudiation?
- 2 Was M+W entitled to an extension of time?
- 3 Did EWH breach its obligations regarding RDF supply and quality management?
Ratio Decidendi
EWH was entitled to terminate the EPC contract for contractor's default and repudiation as M+W was not entitled to an extension of time. M+W's allegations of breach by EWH were either not established or did not cause delay. EWH is entitled to liquidated damages, termination damages, and defect damages. M+W Group GmbH is liable under the parent company guarantee. M+W's counterclaim is dismissed. Outotec's liability for defects is limited to properly notified matters; most contribution claims fail except for defect 17. Outotec is entitled to milestone payments subject to abatement.
Court Disposition
Claimant succeeds in main claims; Defendants' counterclaims mostly dismissed; Third Party partially succeeds in counterclaim for milestone payments.
Orders
- EWH awarded £117,195,361.27 for delay and termination claims.
- EWH awarded £2,152,021.55 for major defect claims.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment