Energy Works (Hull) Limited v MW High Tech Projects UK Limited & Anor
EWH was entitled to terminate the EPC contract for Contractor's Default under clause 44.1(c) as the Delay Damages Cap was exceeded and M+W was not entitled to any extension of time. EWH was also entitled to terminate for repudiatory breach at common law. EWH is entitled to liquidated damages for delay up to termination, and to substantial damages for post-termination completion and defects, subject to contractual exclusions and limitations. M+W's counterclaim is dismissed. Outotec is not liable in contribution for most defects due to lack of notification under the subcontract, but would be liable for certain notified defects if proven. Abatement remains available to M+W as a defence to...
- Parties
- Claimant: Energy Works (Hull) Limited; Defendant: MW High Tech Projects UK Limited; Defendant: M+W Group GmbH; Third Party: Outotec (USA) Inc.
- Jurisdiction
- England and Wales
- Judgment Date
- 20 December 2022
- Procedural Posture
- Commercial Construction Dispute (epc Contract) / Final Judgment After Full Trial
- Outcome
- Judgment for the claimant (EWH); counterclaim dismissed; third-party contribution claims largely dismissed; damages and orders as specified.
- Legal Topics
- Termination for Contractor's Default, Liquidated Damages, Extension of Time, Defects Liability, Contribution Claims, Assignment of Contractual Rights, Abatement, Remedies for Breach, Parent Company Guarantee
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Energy Works (Hull) Limited
Claimant
MW High Tech Projects UK Limited
Defendant
M+W Group GmbH
Defendant
Outotec (USA) Inc.
Third Party
Procedural Posture
Commercial Construction Dispute (epc Contract) / Final Judgment After Full Trial
Legal Issues
- 1 Whether EWH was entitled to terminate the EPC contract for Contractor's Default or repudiation; Whether M+W was entitled to an extension of time; Whether EWH is entitled to liquidated damages and damages for defects; Whether M+W is entitled to a counterclaim; Whether Outotec is liable to contribute to M+W for defects under the subcontract; Effect of assignment of subcontract; Scope of abatement as a defence.
Ratio Decidendi
EWH was entitled to terminate the EPC contract for Contractor's Default under clause 44.1(c) as the Delay Damages Cap was exceeded and M+W was not entitled to any extension of time. EWH was also entitled to terminate for repudiatory breach at common law. EWH is entitled to liquidated damages for delay up to termination, and to substantial damages for post-termination completion and defects, subject to contractual exclusions and limitations. M+W's counterclaim is dismissed. Outotec is not liable in contribution for most defects due to lack of notification under the subcontract, but would be liable for certain notified defects if proven. Abatement remains available to M+W as a defence to...
Court Disposition
Judgment for the claimant (EWH); counterclaim dismissed; third-party contribution claims largely dismissed; damages and orders as specified.
Orders
- EWH entitled to terminate EPC contract for Contractor's Default and/or repudiation;
- EWH awarded liquidated damages for delay (£23,077,331.70);
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment