Southern Electricity Power Distribution PLC v OCU Modus Ltd [2025] EWHC 723 (TCC) (27 March 2025)
The court found that the works carried out by Modus were defective and failed to comply with the Adoption Agreement and good industry practice. The defects were extensive, affecting both the joints and the cables, and posed significant risks of future failure and safety concerns. The court held that SEPD's decision to replace the entire cable circuits, rather than undertake piecemeal joint repairs, was reasonable and proportionate in the circumstances, given the technical risks, the need for long-term reliability, and the commercial impact of outages. The costs incurred by SEPD for the full replacement were recoverable as reasonable costs under the contract.
- Citation
- [2025] EWHC 723 (TCC)
- Parties
- Claimant: Southern Electricity Power Distribution PLC; Defendant: OCU Modus Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 27 March 2025
- Procedural Posture
- TCC Commercial Construction Dispute / Final Judgment After Trial
- Outcome
- Judgment for the Claimant
- Legal Topics
- Defective Works, Measure of Damages, Mitigation of Loss, Causation, Remedial Works, Reasonableness of Reinstatement
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Southern Electricity Power Distribution PLC
Claimant
OCU Modus Limited
Defendant
Procedural Posture
TCC Commercial Construction Dispute / Final Judgment After Trial
Legal Issues
- 1 Whether the works carried out by Modus were defective under the Adoption Agreement
- 2 Whether SEPD was entitled to recover the cost of full cable replacement as reasonable remedial works
- 3 Whether SEPD's remedial solution was proportionate and reasonable
Ratio Decidendi
The court found that the works carried out by Modus were defective and failed to comply with the Adoption Agreement and good industry practice. The defects were extensive, affecting both the joints and the cables, and posed significant risks of future failure and safety concerns. The court held that SEPD's decision to replace the entire cable circuits, rather than undertake piecemeal joint repairs, was reasonable and proportionate in the circumstances, given the technical risks, the need for long-term reliability, and the commercial impact of outages. The costs incurred by SEPD for the full replacement were recoverable as reasonable costs under the contract.
Court Disposition
Judgment for the Claimant
Orders
- Modus to pay SEPD £2,642,237.71, comprising £188,909.96 for interim repairs and £2,453,327.75 for permanent replacement works.
- Interest and costs to be assessed if not agreed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment