Marc Gilbard 2009 Settlement Trust (trustees of) v OD Developments and Projects Ltd [2015] EWHC 70 (TCC) (22 January 2015)
Clause 1.9.3 of the JCT contract allows only one set of proceedings (adjudication, arbitration, or court) commenced within 28 days of the Final Certificate to challenge it; any subsequent proceedings, including adjudication, commenced after the 28-day period cannot challenge the Final Certificate, which is then conclusive evidence except as to matters raised in the timely proceedings.
- Citation
- [2015] EWHC 70 (TCC)
- Parties
- Claimant: The Trustees of the Marc Gilbard 2009 Settlement Trust; Defendant: OD Developments and Projects Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 22 January 2015
- Procedural Posture
- Part 8 Proceedings for Declaratory Relief / Judgment Following Hearing on Interpretation of Contract Clause
- Outcome
- Declaration granted in favour of the claimant as to the interpretation of clause 1.9.3; no declaration granted as to sums due under the Final Certificate.
- Legal Topics
- Final Certificate Conclusivity, JCT Standard Building Contract, Adjudication Rights, Interpretation of Conclusivity Clauses
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
The Trustees of the Marc Gilbard 2009 Settlement Trust
Claimant
OD Developments and Projects Limited
Defendant
Procedural Posture
Part 8 Proceedings for Declaratory Relief / Judgment Following Hearing on Interpretation of Contract Clause
Legal Issues
- 1 Whether a party can commence adjudication proceedings challenging a Final Certificate more than 28 days after its issue when Part 7 proceedings have already been commenced within the 28-day period
- 2 Proper interpretation of clause 1.9.3 of the JCT Standard Building Contract
Ratio Decidendi
Clause 1.9.3 of the JCT contract allows only one set of proceedings (adjudication, arbitration, or court) commenced within 28 days of the Final Certificate to challenge it; any subsequent proceedings, including adjudication, commenced after the 28-day period cannot challenge the Final Certificate, which is then conclusive evidence except as to matters raised in the timely proceedings.
Court Disposition
Declaration granted in favour of the claimant as to the interpretation of clause 1.9.3; no declaration granted as to sums due under the Final Certificate.
Orders
- Declaration that the Final Certificate dated 3 December 2013 is not conclusive evidence in respect of the matters raised in the existing Part 7 claim, but is conclusive evidence in any other proceedings commenced after the 28-day period.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment