Discain Project Services Ltd v. Opecprime Developments Ltd [2001] EWHC Technology 450 (11th December, 2001)
The court found that the contract between Discain and Opecprime was for the supply and installation of structural steelwork balconies, with glazing and non-slip flooring excluded unless expressly agreed as extras. The termination by Opecprime was not justified as Discain had not repudiated the contract. Discain was entitled to payment for works completed up to termination, and Opecprime's counterclaim for defects and incomplete work was only partially substantiated.
- Citation
- [2001] EWHC Technology 450
- Parties
- Claimant: Discain Project Services Ltd; Defendant: Opecprime Developments Ltd
- Jurisdiction
- England and Wales
- Procedural Posture
- Commercial Construction Dispute / Final Judgment
- Outcome
- Claim allowed in part; counterclaim allowed in part
- Legal Topics
- Wrongful Termination, Contractual Interpretation, Payment Disputes, Counterclaims for Defects, Variation of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Discain Project Services Ltd
Claimant
Opecprime Developments Ltd
Defendant
Procedural Posture
Commercial Construction Dispute / Final Judgment
Legal Issues
- 1 Whether Opecprime wrongfully terminated the contract with Discain
- 2 Whether Discain was entitled to payment for works completed
- 3 Whether Opecprime was entitled to counterclaim for defects and incomplete work
Ratio Decidendi
The court found that the contract between Discain and Opecprime was for the supply and installation of structural steelwork balconies, with glazing and non-slip flooring excluded unless expressly agreed as extras. The termination by Opecprime was not justified as Discain had not repudiated the contract. Discain was entitled to payment for works completed up to termination, and Opecprime's counterclaim for defects and incomplete work was only partially substantiated.
Court Disposition
Claim allowed in part; counterclaim allowed in part
Orders
- Opecprime to pay Discain the sum due for completed works up to termination
- Discain to address substantiated defects and incomplete works as identified
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment