Discain Project Services Ltd v. Opecprime Developments Ltd [2001] EWHC Technology 450 (11th December, 2001)

Discain Project Services Ltd v. Opecprime Developments Ltd [2001] EWHC Technology 450 (11th December, 2001)

The court found that the contract between Discain and Opecprime was for the supply and installation of structural steelwork balconies, with glazing and non-slip flooring excluded unless expressly agreed as extras. The termination by Opecprime was not justified as Discain had not repudiated the contract. Discain was entitled to payment for works completed up to termination, and Opecprime's counterclaim for defects and incomplete work was only partially substantiated.

Citation
[2001] EWHC Technology 450
Parties
Claimant: Discain Project Services Ltd; Defendant: Opecprime Developments Ltd
Jurisdiction
England and Wales
Procedural Posture
Commercial Construction Dispute / Final Judgment
Outcome
Claim allowed in part; counterclaim allowed in part
Legal Topics
Wrongful Termination, Contractual Interpretation, Payment Disputes, Counterclaims for Defects, Variation of Contract

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 8
Sign in to unlock

Parties

Discain Project Services Ltd

Claimant

Opecprime Developments Ltd

Defendant

Procedural Posture

Commercial Construction Dispute / Final Judgment

  1. 1 Whether Opecprime wrongfully terminated the contract with Discain
  2. 2 Whether Discain was entitled to payment for works completed
  3. 3 Whether Opecprime was entitled to counterclaim for defects and incomplete work

Ratio Decidendi

The court found that the contract between Discain and Opecprime was for the supply and installation of structural steelwork balconies, with glazing and non-slip flooring excluded unless expressly agreed as extras. The termination by Opecprime was not justified as Discain had not repudiated the contract. Discain was entitled to payment for works completed up to termination, and Opecprime's counterclaim for defects and incomplete work was only partially substantiated.

Court Disposition

Claim allowed in part; counterclaim allowed in part

Orders

  • Opecprime to pay Discain the sum due for completed works up to termination
  • Discain to address substantiated defects and incomplete works as identified