VVB M&E Group Ltd & Anor v Optilan (UK) Ltd [2020] EWHC 4 (TCC) (07 January 2020)
The Vesting Certificates did not require actual payment of the stated sums to trigger vesting; inclusion of the relevant values in the next interim payment, as reflected in the Pay Less Notice 39, sufficed. The Pay Less Notice 39 was the operative document for determining compliance with the vesting condition. There...
Source-derived case information.
- Citation
- [2020] EWHC 4 (TCC)
- Parties
- Claimant: VVB M&E Group Limited; Claimant: VVB Engineering (UK) Limited; Defendant: Optilan (UK) Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 07 January 2020
- Procedural Posture
- Commercial Construction Dispute (delivery Up of Goods) / Final Judgment on Application for Delivery Up; Treated as Summary Judgment on Claim
- Outcome
- Claim allowed; final order for delivery up of goods granted to claimants.
- Legal Topics
- Vesting of Goods, Interpretation of Commercial Contracts, Interim Payments Under Construction Contracts, Set Off and Contra Charges, Effect of Payment Certificates and Pay Less Notices, Implied Terms, Torts (interference With Goods) Act 1977
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
VVB M&E Group Limited
Claimant
VVB Engineering (UK) Limited
Claimant
Optilan (UK) Limited
Defendant
Procedural Posture
Commercial Construction Dispute (delivery Up of Goods) / Final Judgment on Application for Delivery Up; Treated as Summary Judgment on Claim
Legal Issues
- 1 Whether the Vesting Certificates operated to vest ownership of materials in the claimants or Network Rail
- 2 Whether inclusion of the stated value in the next interim payment sufficed to trigger vesting, or whether actual payment was required
- 3 Whether Payment Certificate No. 39 or Pay Less Notice 39 was the operative document for vesting
Ratio Decidendi
The Vesting Certificates did not require actual payment of the stated sums to trigger vesting; inclusion of the relevant values in the next interim payment, as reflected in the Pay Less Notice 39, sufficed. The Pay Less Notice 39 was the operative document for determining compliance with the vesting condition. There was no implied term requiring full and prompt payment under previous certificates as a condition precedent to vesting. Ownership of the materials vested in the claimants (or Network Rail) upon service of the Pay Less Notice 39, even though no net payment was due.
Court Disposition
Claim allowed; final order for delivery up of goods granted to claimants.
Orders
- Optilan (UK) Limited to deliver up the materials identified in the Vesting Certificates to the claimants (or Network Rail, as applicable).
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment