Paddington Churches Housing Association v. Technical and General Guarantee Company Ltd [1999] EWHC Technology 246 (22nd March, 1999)

Paddington Churches Housing Association v. Technical and General Guarantee Company Ltd [1999] EWHC Technology 246 (22nd March, 1999)

The surety is not liable to make any payment under the bond until the employer provides a statement setting out the net established and ascertained damages calculated by reference to clause 27 of the building contract; the action is premature as this condition precedent has not been satisfied.

Source-derived case information.

Citation
[1999] EWHC Technology 246
Parties
Plaintiff: Paddington Churches Housing Association; Defendant: Technical and General Guarantee Company Limited
Jurisdiction
England and Wales
Procedural Posture
Civil / Application for Determination of Construction of Bond Terms and Leave to Amend Statement of Claim
Outcome
Action dismissed; application for leave to amend Statement of Claim refused.
Legal Topics
Performance Bonds, Surety Liability, Building Contract Termination, Calculation of Damages, Condition Precedent to Payment
Construction Law Contract Law Insurance Law Performance Bonds Surety Liability Building Contract Termination Calculation of Damages Condition Precedent to Payment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Paddington Churches Housing Association

Plaintiff

Technical and General Guarantee Company Limited

Defendant

Procedural Posture

Civil / Application for Determination of Construction of Bond Terms and Leave to Amend Statement of Claim

  1. 1 Whether the surety is liable to pay under the performance bond before the employer provides a statement of net established and ascertained damages calculated in accordance with the building contract.
  2. 2 Whether the employer's statement of damages is a condition precedent to the surety's liability.
  3. 3 Whether the proposed amendment to the Statement of Claim would affect the outcome.

Ratio Decidendi

The surety is not liable to make any payment under the bond until the employer provides a statement setting out the net established and ascertained damages calculated by reference to clause 27 of the building contract; the action is premature as this condition precedent has not been satisfied.

Court Disposition

Action dismissed; application for leave to amend Statement of Claim refused.

Orders

  • Application for leave to amend Statement of Claim refused.
  • Action dismissed under RSC Order 14A rule 1(2).