Hayes & Anor (t/a Orchard Construction) v Gallant [2008] EWHC 2726 (TCC) (10 November 2008)
The court found that the claimants were entitled to payment for the value of works completed on both the pool complex and the Old House, assessed on the basis of agreed figures and expert evidence. The defendant's termination of the contract was a repudiatory breach, entitling the claimants to loss of profit as agreed between the parties. The defendant's counterclaim for defective work was considered but limited to substantiated items.
- Citation
- [2008] EWHC 2726 (TCC)
- Parties
- Claimant: Martin John Hayes and Linda Hayes t/a Orchard Construction; Defendant: Peter Gallant
- Jurisdiction
- England and Wales
- Judgment Date
- 10 November 2008
- Procedural Posture
- Civil (construction Dispute) / Judgment After Trial
- Outcome
- Judgment for the claimants in the agreed sums for completed works and loss of profit, subject to set-off for substantiated items in the defendant's counterclaim.
- Legal Topics
- Quantum Meruit, Repudiatory Breach, Loss of Profit, Counterclaim for Defective Work, Remuneration and Overheads, Valuation of Works
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Martin John Hayes and Linda Hayes t/a Orchard Construction
Claimant
Peter Gallant
Defendant
Procedural Posture
Civil (construction Dispute) / Judgment After Trial
Legal Issues
- 1 Whether there was a binding contract or series of contracts for the refurbishment and pool complex works
- 2 Whether the claimants are entitled to the sums claimed for completed works and loss of profit
- 3 Whether the defendant lawfully terminated the contract or repudiated it
Ratio Decidendi
The court found that the claimants were entitled to payment for the value of works completed on both the pool complex and the Old House, assessed on the basis of agreed figures and expert evidence. The defendant's termination of the contract was a repudiatory breach, entitling the claimants to loss of profit as agreed between the parties. The defendant's counterclaim for defective work was considered but limited to substantiated items.
Court Disposition
Judgment for the claimants in the agreed sums for completed works and loss of profit, subject to set-off for substantiated items in the defendant's counterclaim.
Orders
- Defendant to pay claimants £111,794.22 (inclusive of VAT) for pool complex works
- Defendant to pay claimants £40,777.78 for loss of profit on pool complex if liability found
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment