CJ Elvin Building Services Ltd v Noble & Anor

CJ Elvin Building Services Ltd v Noble & Anor

The Defendants were in repudiatory breach for failing to pay sums due; the Claimant was entitled to suspend work and did not repudiate the contract. The Claimant is entitled to payment for works completed, including those performed by a non-CORGI registered subcontractor, as there was no loss flowing from alleged illegality and no evidence of unlawful purpose.

Parties
Claimant: C J Elvin Building Services Limited; Defendant: Peter Noble; Defendant: Alexa Noble
Jurisdiction
England and Wales
Judgment Date
03 April 2003
Procedural Posture
Civil / Judgment
Outcome
Judgment for the Claimant
Legal Topics
Building Contract, Repudiation, Defective Works, Payment Disputes, Implied Terms, Illegality in Contract Performance

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 3 Authorities cited 4 Party arguments 2 Amounts and remedies 3
Sign in to unlock

Parties

C J Elvin Building Services Limited

Claimant

Peter Noble

Defendant

Alexa Noble

Defendant

Procedural Posture

Civil / Judgment

  1. 1 What sum was due to the Claimant for works completed?
  2. 2 Were there defective works or incomplete works?
  3. 3 Did the Claimant repudiate the contract?

Ratio Decidendi

The Defendants were in repudiatory breach for failing to pay sums due; the Claimant was entitled to suspend work and did not repudiate the contract. The Claimant is entitled to payment for works completed, including those performed by a non-CORGI registered subcontractor, as there was no loss flowing from alleged illegality and no evidence of unlawful purpose.

Court Disposition

Judgment for the Claimant

Orders

  • Defendants to pay Claimant £40,016.52 plus interest of £4,262.58, total £44,279.10