Filmflex Movies Ltd v Piksel Ltd [2015] EWHC 426 (Ch) (24 February 2015)
FilmFlex is contractually entitled to delivery up of the source code and related documentation by Piksel and to require Piksel to procure delivery up from the escrow agent. This entitlement arises under clause 9.10.5 of the MSA (triggered by appointment of a third party developer), clause 9.11 (right of access includes right to a copy), and by implication from the ownership and licence provisions in clauses 9.1 and 9.2. The Escrow Agreement does not override these bespoke contractual rights.
- Citation
- [2015] EWHC 426 (Ch)
- Parties
- Claimant: FilmFlex Movies Limited; Defendant: Piksel Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 24 February 2015
- Procedural Posture
- Commercial Contract Dispute / Expedited Trial of Preliminary Issue
- Outcome
- Judgment for the Claimant (FilmFlex) on the preliminary issue.
- Legal Topics
- Software Escrow, Source Code Delivery, Breach of Contract, Interpretation of Commercial Agreements
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
FilmFlex Movies Limited
Claimant
Piksel Limited
Defendant
Procedural Posture
Commercial Contract Dispute / Expedited Trial of Preliminary Issue
Legal Issues
- 1 Whether FilmFlex is entitled to delivery up of source code and documentation under the Master Services Agreement (MSA) and Escrow Agreement
- 2 Whether Piksel is obliged to procure release of source code from escrow upon FilmFlex's appointment of a third party developer
- 3 Whether FilmFlex has a direct right to a copy of the source code from Piksel under the MSA
Ratio Decidendi
FilmFlex is contractually entitled to delivery up of the source code and related documentation by Piksel and to require Piksel to procure delivery up from the escrow agent. This entitlement arises under clause 9.10.5 of the MSA (triggered by appointment of a third party developer), clause 9.11 (right of access includes right to a copy), and by implication from the ownership and licence provisions in clauses 9.1 and 9.2. The Escrow Agreement does not override these bespoke contractual rights.
Court Disposition
Judgment for the Claimant (FilmFlex) on the preliminary issue.
Orders
- Piksel is required to deliver up a copy of the source code and related documentation to FilmFlex.
- Piksel is required to procure the release of the source code and Source Control Database from the escrow agent (NCC) to FilmFlex.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment