Plant Construction Plc v. Clive Adams Associates, JMH Construction Services Limited [1998] EWHC QB 335 (9th March, 1998)
By the parties' conduct, JMH was contractually required to comply with instructions from Ford's engineer, Mr Furley, regarding the form and method of temporary roof support, thereby displacing JMH's design responsibility for those works. However, JMH retained a duty to warn Plant of the inadequacy of the propping, which it failed to discharge adequately. Plant and its engineer, Adams, were also at fault for failing to act on the known inadequacy, and Plant's share of responsibility was predominant. Damages were apportioned 80% to Plant and 20% to JMH.
- Citation
- [1998] EWHC QB 335
- Parties
- Plaintiff: Plant Construction PLC; First Defendant: Clive Adams Associates; Second Defendant: JMH Construction Services Ltd; Third Party (struck Out): Ford Motor Company Ltd
- Jurisdiction
- England and Wales
- Procedural Posture
- Civil / Trial Judgment
- Outcome
- Judgment for the Plaintiff for 20% of agreed damages, with interest as agreed.
- Legal Topics
- Temporary Works Responsibility, Negligence, Contributory Negligence, Variation of Contract, Duty to Warn, Allocation of Design Responsibility
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Plant Construction PLC
Plaintiff
Clive Adams Associates
First Defendant
JMH Construction Services Ltd
Second Defendant
Ford Motor Company Ltd
Third Party (struck Out)
Procedural Posture
Civil / Trial Judgment
Legal Issues
- 1 Who bore responsibility for the design of temporary works (roof propping) under the sub-contract between Plant and JMH?
- 2 Was JMH in breach of a duty of care to warn Plant of inadequate propping?
- 3 Did Plant's conduct amount to contributory negligence and, if so, to what extent should damages be reduced?
Ratio Decidendi
By the parties' conduct, JMH was contractually required to comply with instructions from Ford's engineer, Mr Furley, regarding the form and method of temporary roof support, thereby displacing JMH's design responsibility for those works. However, JMH retained a duty to warn Plant of the inadequacy of the propping, which it failed to discharge adequately. Plant and its engineer, Adams, were also at fault for failing to act on the known inadequacy, and Plant's share of responsibility was predominant. Damages were apportioned 80% to Plant and 20% to JMH.
Court Disposition
Judgment for the Plaintiff for 20% of agreed damages, with interest as agreed.
Orders
- JMH to pay 20% of the agreed damages to Plant Construction PLC, with interest as agreed between the parties.
- JMH to pay 70% of Plant's costs of the action, excluding those incurred against Adams; costs against both Defendants to be apportioned.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment