Jiangsu Guoxin Corporation Ltd v Precious Shipping Public Co Ltd
The shipbuilding contracts expressly provided for extensions of time for delays, including those caused by Buyer’s breach, under Article VIII.1. Therefore, the prevention principle does not apply. The Seller was not entitled to extend the Delivery and/or Cancellation Date without operating or exercising the relevant contractual machinery, including giving notice as required by Article VIII.2. Notification requirements are mandatory for extension of time unless a more specific regime applies. Modifications and Buyer’s payment defaults are governed by their own contractual provisions, and no extension is available without compliance.
- Parties
- Claimant: Jiangsu Guoxin Corporation Ltd (formerly known as Sainty Marine Corporation Ltd); Respondent: Precious Shipping Public Co. Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 30 April 2020
- Procedural Posture
- Arbitration Appeal / Judgment on Appeal Under Section 69 of the Arbitration Act 1996
- Outcome
- Appeals dismissed
- Legal Topics
- Extension of Time Clauses, Prevention Principle, Notification Requirements, Shipbuilding Contracts, Implied Terms
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Jiangsu Guoxin Corporation Ltd (formerly known as Sainty Marine Corporation Ltd)
Claimant
Precious Shipping Public Co. Ltd
Respondent
Procedural Posture
Arbitration Appeal / Judgment on Appeal Under Section 69 of the Arbitration Act 1996
Legal Issues
- 1 Whether the prevention principle applies to SAJ form shipbuilding contracts with express extension of time provisions
- 2 Whether the Seller must give notice of delay events or exercise contractual machinery to rely on delay events when the Buyer purports to terminate for accumulated delay
- 3 Interpretation of Article VIII.1 and VIII.2 regarding permissible delays and notification
Ratio Decidendi
The shipbuilding contracts expressly provided for extensions of time for delays, including those caused by Buyer’s breach, under Article VIII.1. Therefore, the prevention principle does not apply. The Seller was not entitled to extend the Delivery and/or Cancellation Date without operating or exercising the relevant contractual machinery, including giving notice as required by Article VIII.2. Notification requirements are mandatory for extension of time unless a more specific regime applies. Modifications and Buyer’s payment defaults are governed by their own contractual provisions, and no extension is available without compliance.
Court Disposition
Appeals dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment