VMA Services Limited v Project One London Limited
Where an adjudicator determines that a notified sum is immediately due to a respondent, the adjudicator has jurisdiction to order payment and the decision is enforceable; requiring a further adjudication would be contrary to the policy of the Act and Scheme.
Source-derived case information.
- Parties
- Claimant: VMA Services Limited; Defendant: Project One London Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 21 July 2025
- Procedural Posture
- Summary Judgment Application / Judgment
- Outcome
- Summary judgment granted; Decision enforced
- Legal Topics
- Adjudication Enforcement, Payment Notices, Jurisdiction of Adjudicator, Smash and Grab Adjudication
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
VMA Services Limited
Claimant
Project One London Limited
Defendant
Procedural Posture
Summary Judgment Application / Judgment
Legal Issues
- 1 Whether the adjudicator had jurisdiction to make a monetary award in favour of the respondent to the adjudication
- 2 Whether the Decision should be enforced against the defendant
Ratio Decidendi
Where an adjudicator determines that a notified sum is immediately due to a respondent, the adjudicator has jurisdiction to order payment and the decision is enforceable; requiring a further adjudication would be contrary to the policy of the Act and Scheme.
Court Disposition
Summary judgment granted; Decision enforced
Orders
- POL shall pay VMA the notified sum of £106,434.88 plus interest from 3 August 2024 to 10 February 2025 in the sum of £5,598.77, accruing at £29.16 per day after 10 February 2025; VAT to be added as applicable; payment forthwith
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment