Triple Point Technology, Inc v PTT Public Company Ltd
The CTRM Contract was the sole contract governing the parties' relationship, including software licensing and implementation. Payment was only due on achievement of milestones, not on fixed dates in the Order Forms. TPT was responsible for delay and failure of the project due to inadequate project management, resources, and failure to integrate software as required. There was no agreement to suspend contractual timeframes, and force majeure did not excuse TPT's non-performance. PTT lawfully terminated the contract under its terms and at common law. PTT is entitled to damages for procurement of an alternative system, wasted hardware costs, and liquidated damages for delay, but such damages...
- Parties
- Claimant: Triple Point Technology, Inc.; Defendant: PTT Public Company Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 23 August 2017
- Procedural Posture
- Commercial Contract Dispute / Judgment After Full Trial
- Outcome
- Judgment for Defendant (PTT) on main claims and counterclaims, subject to limitation of liability cap.
- Legal Topics
- Software Implementation Contracts, Breach of Contract, Liquidated Damages, Limitation of Liability, Force Majeure, Implied Terms, Project Management Obligations
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Triple Point Technology, Inc.
Claimant
PTT Public Company Limited
Defendant
Procedural Posture
Commercial Contract Dispute / Judgment After Full Trial
Legal Issues
- 1 Whether there was a single contract (CTRM Contract) or separate contracts for software licensing and implementation services
- 2 Whether TPT was entitled to payment under Order Forms or only under CTRM Contract milestones
- 3 Whether TPT or PTT was responsible for delay and failure of the project
Ratio Decidendi
The CTRM Contract was the sole contract governing the parties' relationship, including software licensing and implementation. Payment was only due on achievement of milestones, not on fixed dates in the Order Forms. TPT was responsible for delay and failure of the project due to inadequate project management, resources, and failure to integrate software as required. There was no agreement to suspend contractual timeframes, and force majeure did not excuse TPT's non-performance. PTT lawfully terminated the contract under its terms and at common law. PTT is entitled to damages for procurement of an alternative system, wasted hardware costs, and liquidated damages for delay, but such damages...
Court Disposition
Judgment for Defendant (PTT) on main claims and counterclaims, subject to limitation of liability cap.
Orders
- TPT's claims for payment under Order Forms and for services are dismissed.
- PTT is entitled to damages for procurement of an alternative system (US$10,574,756.78), wasted hardware costs (US$630,000), and liquidated damages for delay (US$3,459,278.40), subject to a cap of US$1,038,000 under Article 12.3.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment