Triple Point Technology, Inc v PTT Public Company Ltd
Liquidated damages for delay under Article 5.3 are not recoverable where the contractor never achieves completion; damages for breach are subject to the Article 12.3 cap, which encompasses all breaches including delay. Payment is only due on milestone completion, not calendar dates in order forms.
- Parties
- Claimant/appellant: Triple Point Technology, Inc.; Respondent: PTT Public Company Ltd
- Jurisdiction
- England and Wales
- Judgment Date
- 05 March 2019
- Procedural Posture
- Civil Appeal / Court of Appeal Judgment
- Outcome
- Appeal allowed in part, cross-appeal dismissed.
- Legal Topics
- Liquidated Damages, Contract Interpretation, Limitation of Liability, Termination, Payment Provisions
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Triple Point Technology, Inc.
Claimant/appellant
PTT Public Company Ltd
Respondent
Procedural Posture
Civil Appeal / Court of Appeal Judgment
Legal Issues
- 1 Whether payment was due on milestone completion or calendar dates stated in order forms
- 2 Whether Triple Point was entitled to suspend work for non-payment
- 3 Whether liquidated damages for delay are recoverable when contractor never achieves completion
Ratio Decidendi
Liquidated damages for delay under Article 5.3 are not recoverable where the contractor never achieves completion; damages for breach are subject to the Article 12.3 cap, which encompasses all breaches including delay. Payment is only due on milestone completion, not calendar dates in order forms.
Court Disposition
Appeal allowed in part, cross-appeal dismissed.
Orders
- Triple Point's claim dismissed.
- Judge's award of liquidated damages for delay set aside.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment