Oaxaca Limited t/a Wahaca v QIC Europe Limited
Summary judgment on the coverage issue is refused because there are unresolved factual and evidential issues regarding loss and the occurrence of COVID-19 in the immediate vicinity of the premises. Summary judgment is granted on the construction issue only, with permission to appeal, as the point is closed at this level but arguable at a higher level. The application for interim payment fails because the court is not satisfied on the evidence that the claimants would obtain judgment for a substantial amount of money at trial.
- Parties
- Claimant: Oaxaca Limited T/A Wahaca; Defendant: QIC Europe Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 11 October 2024
- Procedural Posture
- Civil (commercial Insurance) / Summary Judgment Application and Interim Payment Application
- Outcome
- Summary judgment on coverage refused; summary judgment on construction issue granted with permission to appeal; interim payment application refused.
- Legal Topics
- Business Interruption Insurance, COVID 19 Related Claims, Policy Construction, Summary Judgment, Interim Payment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Oaxaca Limited T/A Wahaca
Claimant
QIC Europe Limited
Defendant
Procedural Posture
Civil (commercial Insurance) / Summary Judgment Application and Interim Payment Application
Legal Issues
- 1 Whether the claimants are entitled to summary judgment on the construction of the business interruption insurance policy (NDDA clause) in relation to COVID-19 related losses
- 2 Whether the claimants are entitled to summary judgment on coverage under the policy for business interruption losses
- 3 Whether the claimants are entitled to an interim payment under CPR r 25.7
Ratio Decidendi
Summary judgment on the coverage issue is refused because there are unresolved factual and evidential issues regarding loss and the occurrence of COVID-19 in the immediate vicinity of the premises. Summary judgment is granted on the construction issue only, with permission to appeal, as the point is closed at this level but arguable at a higher level. The application for interim payment fails because the court is not satisfied on the evidence that the claimants would obtain judgment for a substantial amount of money at trial.
Court Disposition
Summary judgment on coverage refused; summary judgment on construction issue granted with permission to appeal; interim payment application refused.
Orders
- Summary judgment on the construction issue granted in favour of the claimants with permission to appeal.
- Summary judgment on the coverage issue refused.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment