Sitol Limited v Finegold & Anor [2018] EWHC 3969 (TCC) (18 December 2018)

Sitol Limited v Finegold & Anor [2018] EWHC 3969 (TCC) (18 December 2018)

The contract for the tiling works was between Sitol Limited and the Finegolds, with Proman acting as agent/project manager, not as main contractor. However, the adjudication was commenced out of time as the dispute had crystallised by 19 February 2018, and notification was not given within four weeks as required by...

Source-derived case information.

Citation
[2018] EWHC 3969 (TCC)
Parties
Claimant: Sitol Limited; Defendant: R. Finegold; Defendant: H. Finegold
Jurisdiction
England and Wales
Judgment Date
18 December 2018
Procedural Posture
Application to Enforce Adjudication Decision (summary Judgment) / High Court (technology & Construction Court) Judgment
Outcome
Application dismissed
Legal Topics
Adjudication Enforcement, Summary Judgment, Contract Formation, Agency, Notification of Dispute
Construction Law Contract Law Civil Procedure Adjudication Enforcement Summary Judgment Contract Formation Agency Notification of Dispute

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Sitol Limited

Claimant

R. Finegold

Defendant

H. Finegold

Defendant

Procedural Posture

Application to Enforce Adjudication Decision (summary Judgment) / High Court (technology & Construction Court) Judgment

  1. 1 Whether the contract for tiling works was between Sitol Limited and the Finegolds or with Proman UK Limited as main contractor
  2. 2 Whether the adjudication was commenced within the contractual time limit for notification of dispute

Ratio Decidendi

The contract for the tiling works was between Sitol Limited and the Finegolds, with Proman acting as agent/project manager, not as main contractor. However, the adjudication was commenced out of time as the dispute had crystallised by 19 February 2018, and notification was not given within four weeks as required by the contract, so enforcement must be refused.

Court Disposition

Application dismissed

Orders

  • Summary judgment refused
  • No enforcement of adjudicator's decision