The Secretary of State for the Home Department v Raytheon Systems Ltd [2015] EWHC 311 (TCC) (17 February 2015)
The award was set aside in its entirety because the tribunal's failure to address critical issues of delay responsibility and quantum constituted serious irregularity causing substantial injustice, and it would be inappropriate to remit due to the risk of subconscious bias, passage of time, and lack of confidence in the tribunal's ability to reconsider impartially.
- Citation
- [2015] EWHC 311 (TCC)
- Parties
- Claimant: The Secretary of State for the Home Department; Defendant: Raytheon Systems Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 17 February 2015
- Procedural Posture
- Application Under Section 68(2)(d) Arbitration Act 1996 / Post Judgment, Consequential Hearing on Remission or Setting Aside, Costs
- Outcome
- Award set aside in total; matter to be resolved by a different arbitral tribunal.
- Legal Topics
- Serious Irregularity, Remission Vs Setting Aside Arbitral Award, Costs in Arbitration Challenges
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
The Secretary of State for the Home Department
Claimant
Raytheon Systems Limited
Defendant
Procedural Posture
Application Under Section 68(2)(d) Arbitration Act 1996 / Post Judgment, Consequential Hearing on Remission or Setting Aside, Costs
Legal Issues
- 1 Whether the arbitral award should be remitted or set aside due to serious irregularity under Section 68(2)(d) Arbitration Act 1996
- 2 Appropriateness of remission versus setting aside
- 3 Costs disposition following successful challenge
Ratio Decidendi
The award was set aside in its entirety because the tribunal's failure to address critical issues of delay responsibility and quantum constituted serious irregularity causing substantial injustice, and it would be inappropriate to remit due to the risk of subconscious bias, passage of time, and lack of confidence in the tribunal's ability to reconsider impartially.
Court Disposition
Award set aside in total; matter to be resolved by a different arbitral tribunal.
Orders
- Raytheon Systems Limited to pay 80% of The Secretary of State for the Home Department's costs, assessed on the standard basis.
- Raytheon Systems Limited to pay £146,000 as interim payment on account of costs.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment