Inovatech EMEA Ltd & Anor v Nuttall [2010] EWHC 226 (TCC) (22 January 2010)
It is not appropriate at this stage to strike out the proceedings; Claimants are entitled to pursue their application to set aside the default judgment, but must pay the Defendant's costs for abortive hearings due to their delay, and the action is stayed until costs are paid.
- Citation
- [2010] EWHC 226 (TCC)
- Parties
- Claimant: InovaTech EMEA Limited; Claimant: PowerNet Communications (Pty) Limited; Defendant: Richard Nuttall
- Jurisdiction
- England and Wales
- Judgment Date
- 22 January 2010
- Procedural Posture
- Civil / Case Management Conference; Application to Strike Out; Costs Order
- Outcome
- Claim not struck out; action stayed pending payment of costs.
- Legal Topics
- Default Judgment, Application to Set Aside Judgment, Strike Out Proceedings, Costs Order, Case Management, Contractual Performance
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
InovaTech EMEA Limited
Claimant
PowerNet Communications (Pty) Limited
Claimant
Richard Nuttall
Defendant
Procedural Posture
Civil / Case Management Conference; Application to Strike Out; Costs Order
Legal Issues
- 1 Whether proceedings should be struck out for delay and non-compliance with directions
- 2 Whether Claimants should pay costs for abortive hearings
- 3 Whether Claimants are entitled to pursue application to set aside default judgment
Ratio Decidendi
It is not appropriate at this stage to strike out the proceedings; Claimants are entitled to pursue their application to set aside the default judgment, but must pay the Defendant's costs for abortive hearings due to their delay, and the action is stayed until costs are paid.
Court Disposition
Claim not struck out; action stayed pending payment of costs.
Orders
- Claimants to pay Defendant's costs for hearings on 6 November 2009 and 22 January 2010 on indemnity basis, summarily assessed at £4197.68.
- Costs to be paid within seven days of postscript (11 February 2010); if not paid by 25 February 2010, Claim stayed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment