Systems Pipework Ltd v Rotary Building Services Ltd [2017] EWHC 3235 (TCC) (12 December 2017)
The 2 September 2016 assessment was not a proper notification of the amount due for payment under clause 28.6, as it failed to specify the sum due, did not reference the clause, and required further calculation. Even if it had been a proper notification, the claimant's written dissent by commencing adjudication prevented any deemed agreement or binding effect under the contract.
- Citation
- [2017] EWHC 3235 (TCC)
- Parties
- Claimant: Systems Pipework Limited; Defendant: Rotary Building Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 12 December 2017
- Procedural Posture
- CPR Part 8 Proceedings / Judgment After Hearing
- Outcome
- Judgment for the claimant; declarations granted as sought.
- Legal Topics
- Final Account Procedures, Notification Requirements, Interpretation of Construction Contracts, Adjudication, Time Limits and Loss of Rights
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Systems Pipework Limited
Claimant
Rotary Building Services Limited
Defendant
Procedural Posture
CPR Part 8 Proceedings / Judgment After Hearing
Legal Issues
- 1 What notification was required under clause 28.6 for it to be binding?
- 2 Was the 2 September 2016 assessment a proper notification under clause 28.6?
- 3 If proper notification was sent, was there valid dissent by the claimant?
Ratio Decidendi
The 2 September 2016 assessment was not a proper notification of the amount due for payment under clause 28.6, as it failed to specify the sum due, did not reference the clause, and required further calculation. Even if it had been a proper notification, the claimant's written dissent by commencing adjudication prevented any deemed agreement or binding effect under the contract.
Court Disposition
Judgment for the claimant; declarations granted as sought.
Orders
- Declaration that the 2 September 2016 assessment was not a proper notification under clause 28.6.
- Declaration that, if it was a notification, the claimant's dissent prevented any deemed agreement or binding effect.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment