MJS Projects (March) Ltd v RPS Consulting Services Ltd [2025] EWHC 831 (TCC) (09 April 2025)
The Claimant failed to prove on the balance of probabilities that any breach of duty or negligence by the Defendant was an effective cause of the damage to the container yard by December 2017. The evidence established that multiple and significant construction errors, including use of incorrect dowel size, omission and misplacement of dowels, missing mesh, inadequate sub-base and capping, and poor workmanship, were the primary causes of the damage. The Defendant's design, while not perfect, did not fall below the standard of reasonable skill and care required of a competent professional. The claim was pleaded solely on the basis that the Defendant's breach was the cause of the damage, and...
- Citation
- [2025] EWHC 831 (TCC)
- Parties
- Claimant: MJS Projects (March) Limited; Defendant: RPS Consulting Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 09 April 2025
- Procedural Posture
- TCC Trial Judgment / Post Trial, Final Judgment
- Outcome
- Claim dismissed
- Legal Topics
- Defective Design, Breach of Contract, Negligence, Causation, Concurrent Liability, Quantum of Damages
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
MJS Projects (March) Limited
Claimant
RPS Consulting Services Limited
Defendant
Procedural Posture
TCC Trial Judgment / Post Trial, Final Judgment
Legal Issues
- 1 What was the damage to the container yard by December 2017?
- 2 Were there construction errors and did they cause or contribute to the damage?
- 3 Was the Defendant's design for the slot drains negligent or in breach of contract?
Ratio Decidendi
The Claimant failed to prove on the balance of probabilities that any breach of duty or negligence by the Defendant was an effective cause of the damage to the container yard by December 2017. The evidence established that multiple and significant construction errors, including use of incorrect dowel size, omission and misplacement of dowels, missing mesh, inadequate sub-base and capping, and poor workmanship, were the primary causes of the damage. The Defendant's design, while not perfect, did not fall below the standard of reasonable skill and care required of a competent professional. The claim was pleaded solely on the basis that the Defendant's breach was the cause of the damage, and...
Court Disposition
Claim dismissed
Orders
- Claim dismissed in its entirety
- No order as to damages against the Defendant
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment