MJS Projects (March) Limited v RPS Consulting Services Limited
The claim failed because all damage identified by December 2017 was caused by construction errors, not by any negligence or breach in the Defendant’s design. The Defendant’s final design was adequate and complied with competent professional standards. No breach of duty or causation was established against the Defendant.
- Parties
- Claimant: MJS Projects (March) Limited; Defendant: RPS Consulting Services Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 04 October 2025
- Procedural Posture
- Civil / Final Judgment After Trial
- Outcome
- Claim dismissed
- Legal Topics
- Defective Design, Breach of Contract, Concurrent Causes, Expert Evidence, Causation, Duty of Care
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
MJS Projects (March) Limited
Claimant
RPS Consulting Services Limited
Defendant
Procedural Posture
Civil / Final Judgment After Trial
Legal Issues
- 1 What was the damage to the container yard by December 2017?
- 2 Were there construction errors and did they cause or contribute to the damage?
- 3 Was the Defendant’s design negligent or in breach of contract?
Ratio Decidendi
The claim failed because all damage identified by December 2017 was caused by construction errors, not by any negligence or breach in the Defendant’s design. The Defendant’s final design was adequate and complied with competent professional standards. No breach of duty or causation was established against the Defendant.
Court Disposition
Claim dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment