Manor Co-Living Limited v RY Construction Limited
The Adjudicator did not breach natural justice as he considered and rejected the claimant's defence of common law termination on its merits, finding no valid acceptance of repudiatory breach, and it was unnecessary to consider substantive repudiatory conduct. The case that conduct constituted acceptance was not advanced in the adjudication.
- Parties
- Claimant: Manor Co-Living Limited; Defendant: RY Construction Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 27 October 2022
- Procedural Posture
- Part 8 Claim / Judgment
- Outcome
- Claim dismissed
- Legal Topics
- Adjudication, Termination of Contract, Repudiatory Breach, Natural Justice
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Manor Co-Living Limited
Claimant
RY Construction Limited
Defendant
Procedural Posture
Part 8 Claim / Judgment
Legal Issues
- 1 Whether the Adjudicator breached natural justice by failing to consider the claimant's defence of common law entitlement to terminate the contract
- 2 Whether the claimant's conduct amounted to acceptance of repudiatory breach
- 3 Whether the contractual termination was valid
Ratio Decidendi
The Adjudicator did not breach natural justice as he considered and rejected the claimant's defence of common law termination on its merits, finding no valid acceptance of repudiatory breach, and it was unnecessary to consider substantive repudiatory conduct. The case that conduct constituted acceptance was not advanced in the adjudication.
Court Disposition
Claim dismissed
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment