Cleveland Bridge UK Ltd v Sarens (UK) Ltd [2018] EWHC 751 (TCC) (10 April 2018)

Cleveland Bridge UK Ltd v Sarens (UK) Ltd [2018] EWHC 751 (TCC) (10 April 2018)

The parties did not reach agreement on a mechanism for liquidated damages or a cap on delay damages in the subcontract. The only agreed term was that any liquidated damages would be limited to 10% of the subcontract price, but no operative mechanism for liquidated damages was agreed. There was no agreement that...

Source-derived case information.

Citation
[2018] EWHC 751 (TCC)
Parties
Claimant: Cleveland Bridge UK Limited; Defendant: Sarens (UK) Limited
Jurisdiction
England and Wales
Judgment Date
10 April 2018
Procedural Posture
Commercial Construction Contract Dispute / Final Judgment After Trial Following Adjudication
Outcome
Declarations granted in favour of CBUK's primary case; Sarens' counterclaim and alternative cases dismissed.
Legal Topics
Formation of Contract, Interpretation of Contract Terms, Liquidated Damages, Delay Damages, Course of Dealing, Implied Terms
Construction Law Contract Law Formation of Contract Interpretation of Contract Terms Liquidated Damages Delay Damages Course of Dealing Implied Terms

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Cleveland Bridge UK Limited

Claimant

Sarens (UK) Limited

Defendant

Procedural Posture

Commercial Construction Contract Dispute / Final Judgment After Trial Following Adjudication

  1. 1 Whether the parties agreed to a cap on delay/liquidated damages in the subcontract and, if so, its scope and application
  2. 2 Whether the subcontract included a requirement for proof of negligence for damages to be recoverable
  3. 3 Whether a term should be implied into the subcontract limiting Sarens' liability for delay damages

Ratio Decidendi

The parties did not reach agreement on a mechanism for liquidated damages or a cap on delay damages in the subcontract. The only agreed term was that any liquidated damages would be limited to 10% of the subcontract price, but no operative mechanism for liquidated damages was agreed. There was no agreement that damages would only be recoverable upon proof of negligence. No term should be implied into the subcontract limiting Sarens' liability for delay damages beyond what was expressly agreed.

Court Disposition

Declarations granted in favour of CBUK's primary case; Sarens' counterclaim and alternative cases dismissed.

Orders

  • Declaration that there was no agreement between the parties in relation to liquidated damages or a cap thereon, save that any liquidated damages would be limited to 10% of the subcontract price.
  • No operative mechanism for liquidated damages was agreed.