Balfour Beatty Construction v Serco Ltd.
Serco is obliged to pay Balfour Beatty the sum awarded by the adjudicator and is not entitled to set off liquidated and ascertained damages, as the adjudicator did not determine entitlement to such damages for the period after 7th June 2004; summary judgment is granted to Balfour Beatty.
- Parties
- Claimant: Balfour Beatty Construction Limited; Defendant: Serco Limited
- Jurisdiction
- England and Wales
- Judgment Date
- 21 December 2004
- Procedural Posture
- Application for Summary Judgment / Judgment
- Outcome
- summary judgment granted for claimant
- Legal Topics
- Adjudication Enforcement, Liquidated Damages, Extension of Time, Withholding Notices
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Balfour Beatty Construction Limited
Claimant
Serco Limited
Defendant
Procedural Posture
Application for Summary Judgment / Judgment
Legal Issues
- 1 Is the claimant entitled to summary judgment enforcing the adjudicator’s award?
- 2 Can the defendant set off liquidated and ascertained damages against sums awarded by the adjudicator?
- 3 Did the adjudicator determine the entitlement to liquidated damages for the period after 7th June 2004?
Ratio Decidendi
Serco is obliged to pay Balfour Beatty the sum awarded by the adjudicator and is not entitled to set off liquidated and ascertained damages, as the adjudicator did not determine entitlement to such damages for the period after 7th June 2004; summary judgment is granted to Balfour Beatty.
Court Disposition
summary judgment granted for claimant
Orders
- Serco to pay Balfour Beatty the sum awarded by the adjudicator (£620,664 plus VAT)
- No stay granted
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment