Balfour Beatty Construction v Serco Ltd.

Balfour Beatty Construction v Serco Ltd.

Serco is obliged to pay Balfour Beatty the sum awarded by the adjudicator and is not entitled to set off liquidated and ascertained damages, as the adjudicator did not determine entitlement to such damages for the period after 7th June 2004; summary judgment is granted to Balfour Beatty.

Parties
Claimant: Balfour Beatty Construction Limited; Defendant: Serco Limited
Jurisdiction
England and Wales
Judgment Date
21 December 2004
Procedural Posture
Application for Summary Judgment / Judgment
Outcome
summary judgment granted for claimant
Legal Topics
Adjudication Enforcement, Liquidated Damages, Extension of Time, Withholding Notices

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Balfour Beatty Construction Limited

Claimant

Serco Limited

Defendant

Procedural Posture

Application for Summary Judgment / Judgment

  1. 1 Is the claimant entitled to summary judgment enforcing the adjudicator’s award?
  2. 2 Can the defendant set off liquidated and ascertained damages against sums awarded by the adjudicator?
  3. 3 Did the adjudicator determine the entitlement to liquidated damages for the period after 7th June 2004?

Ratio Decidendi

Serco is obliged to pay Balfour Beatty the sum awarded by the adjudicator and is not entitled to set off liquidated and ascertained damages, as the adjudicator did not determine entitlement to such damages for the period after 7th June 2004; summary judgment is granted to Balfour Beatty.

Court Disposition

summary judgment granted for claimant

Orders

  • Serco to pay Balfour Beatty the sum awarded by the adjudicator (£620,664 plus VAT)
  • No stay granted