Cleveland Bridge UK Ltd v Severfield - Rowen Structures Ltd
CBUK was in breach of contract for failing to deliver fabricated steel in accordance with the December Programme, and was not entitled to damages for delay as it failed to prove that delays were caused by SRS. SRS was entitled to damages for proven delay and defects, but only to the extent proven and causally linked to CBUK's breaches. The net sum due to CBUK was subject to set-off for SRS's counterclaim.
- Parties
- Claimant: Cleveland Bridge UK Limited; Defendant: Severfield – Rowen Structures Limited (formerly Severfield-Reeve Structures Limited)
- Jurisdiction
- England and Wales
- Judgment Date
- 21 December 2012
- Procedural Posture
- Civil (construction Contract Dispute) / Judgment After Full Trial
- Outcome
- Judgment for Claimant in part, with set-off for Defendant's counterclaim; liability for certain NCRs deferred for later quantification.
- Legal Topics
- Delay in Construction Contracts, Breach of Contract, Damages for Delay, Variation Claims, Defective Workmanship, Mitigation of Loss
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Cleveland Bridge UK Limited
Claimant
Severfield – Rowen Structures Limited (formerly Severfield-Reeve Structures Limited)
Defendant
Procedural Posture
Civil (construction Contract Dispute) / Judgment After Full Trial
Legal Issues
- 1 Whether CBUK was entitled to additional payment for delays and variations under the sub-contract
- 2 Whether SRS was entitled to set-off and counterclaim for delay and defects
- 3 Which programme governed the parties' obligations and liability for delay
Ratio Decidendi
CBUK was in breach of contract for failing to deliver fabricated steel in accordance with the December Programme, and was not entitled to damages for delay as it failed to prove that delays were caused by SRS. SRS was entitled to damages for proven delay and defects, but only to the extent proven and causally linked to CBUK's breaches. The net sum due to CBUK was subject to set-off for SRS's counterclaim.
Court Disposition
Judgment for Claimant in part, with set-off for Defendant's counterclaim; liability for certain NCRs deferred for later quantification.
Orders
- CBUK entitled to £928,472.55 plus VAT, subject to set-off of £824,478.49 due to SRS for delay and defects.
- VAT to be applied to any net balance due after set-off.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment